What Is a Submittal Register?

Last reviewed: September 2026

A submittal register is the project's list of required submittals, usually with the specification section, the responsible contractor, the date due, the date received, the action, and whether a resubmittal is open. People also call it a submittal log.

Also called
Submittal log
Built from
The submittal articles in the specifications
Required by
Usually Division 01, early after award
Tracks
Due dates, receipt, review action, and resubmittals
Used by
Contractor, architect, and the trades
Not the same as
The submittal itself

Definition

Submittal register

Division 01 tells the contractor to prepare it from the specifications, often within a set number of days after award. Each technical section's submittal article becomes rows. The register is a management tool. It does not replace the submittals themselves, and a row marked approved is only as good as the stamped document in the file. Schedulers tie long-lead rows to the procurement activities. A register that is not updated becomes a record of intentions.

In depth

What a useful row contains

Spec section, item, type (product data, shop drawing, sample), trade, date needed in the field, date due to the reviewer, date sent, action, and resubmittal date. A row without a needed-by date cannot be scheduled.

Group by section so a missing article is obvious. A register that lists only what trades have already sent hides the items nobody picked up.

Tie it to procurement

The submittal schedule and the construction schedule have to agree on long-lead items. A switchgear submittal approved after the gear had to be released is a register that was not connected to the work.

Review durations come from Division 01. The register should use that duration, not a hope.

Status words should match the stamps

Use the same actions the spec uses: approved, approved as noted, revise and resubmit, rejected. Inventing 'in process' for a month hides a ball in someone's court.

Resubmittals get a new line or a clear suffix. Overwriting the rejected date destroys the history a delay claim will ask for.

The spec is the checklist

Someone should compare the register to every submittal article, including Division 01 closeout items and mockups. Trades omit items that have no product to sell, such as qualification data, and those rows still matter.

Delegated-design submittals need their own rows. They take longer because they include engineering.

The log is not the file

The approved PDF, with the stamp, is the record. The register points to it. A status of approved with no file attached will not satisfy closeout or a dispute.

At handover, the register should show closeout submittals as clearly as construction ones. O&M and warranties are rows, not an afterthought folder.

Examples

Submittal register on a real project

  • 01

    The register lists section 08 11 13 shop drawings due 30 days after notice to proceed, with a 14 day review, matching Division 01.

  • 02

    A revise-and-resubmit on the curtain wall keeps the original row and adds a resubmittal date. The release date in the schedule moves with it.

  • 03

    Closeout warranties are rows from the start, so they are not discovered in the last month.

FAQ

Frequently asked questions

It is the log of submittals the specifications require, with dates and review status. It is also called a submittal log.

The contractor, from the specification sections, on the timetable Division 01 states. The architect uses it to see what is coming and what is late.

The register is the full list and status. The schedule is the timing, often tied to the construction schedule. Many projects combine them in one spreadsheet.

No. It means they are listed. Approval is the stamped action on each item, and only for the scope of that stamp.
Accelerating the design and construction of the built world.

Unlock the value of your institutional knowledge—organized, connected, and grounded in your team's critical workflows with Nomic.

Start for free
What Is a Submittal Register? | Nomic