What Is Division 01?

Last reviewed: September 2026

Division 01 is the MasterFormat division for general requirements. It states the administrative rules of the project: how submittals work, how meetings run, what closeout requires, and which temporary facilities the contractor provides. It applies to every trade, not to one product.

MasterFormat
Division 01, General Requirements
Applies to
All specification sections and all trades
Typical sections
Submittals, quality, temporary facilities, closeout
Not the same as
The general conditions of the contract
Lives in
The project manual, in front of the technical sections
Common clash
A technical section that invents its own submittal rules

Definition

Division 01

The technical specifications, from Division 02 onward, say what to build. Division 01 says how the project is administered. It is part of the specifications, which makes it part of the contract documents. It is not the same document as the general conditions. The general conditions are the contract's legal terms, often AIA A201 or a custom equivalent. Division 01 is where those terms get project-specific procedures. A submittal requirement that appears only in a technical section and contradicts Division 01 will be argued on day one.

In depth

What you actually find there

Summary of work, allowances, alternates, unit prices, substitution procedures, coordination, project meetings, submittal procedures, quality requirements, temporary facilities, product storage, and closeout submittals. The exact sections vary. The role does not.

Section 01 33 00, or its successor in the project's numbering, is where submittal lead times, electronic procedures, and resubmittal rules usually sit. Trade sections then list what must be submitted, and they should point back here for how.

Division 01 and the general conditions

A201 and similar documents cover the rights and duties of owner, architect, and contractor. Division 01 tells the contractor how this project wants RFIs, submittals, schedules, and closeout formatted. If they conflict, the agreement's precedence clause decides. They should be written so they do not conflict.

Supplementary conditions modify the general conditions. They are not Division 01 either. Three places can change the same duty. Someone has to read all three before the project manual is issued.

Bidders miss Division 01 because it has no quantity

Temporary power, dumpsters, mockups, extraordinary closeout binders, and BIM coordination requirements live here and cost money. An estimate that prices only Divisions 03 through 33 will be short.

Allowances and alternates defined in Division 01 have to match the bid form. A mismatch is a bid-day dispute about what number was requested.

One procedure, many sections

Each technical section should say which items are submitted. Division 01 should say how many copies, what a deviation looks like, and how long review takes. When a trade spec shortens the review period on its own, the contractor will cite Division 01 and the designer will cite the trade spec.

Closeout requirements, including O&M manuals and record drawings, belong here and in the technical sections' closeout articles. Say which document controls the format.

Boilerplate that was not edited

Division 01 templates mention procedures the project does not use, or they omit ones it does. An unedited section that requires a trailer the site cannot hold, or a process the owner does not run, is still a specification until you change it.

Edit it against the agreement and the supplementary conditions before the book is issued. Adding project procedures by email after award is a change.

Examples

Division 01 on a real project

  • 01

    Section 01 33 00 gives the architect 14 days to review submittals. A paint section that says 5 days is revised to point at 01 33 00.

  • 02

    Division 01 requires a coordinated shop-drawing overlay above corridors. The mechanical bid includes that work because the estimator read it.

  • 03

    Allowances in 01 21 00 match the bid form line items. No third allowance exists only in a narrative.

FAQ

Frequently asked questions

It is the MasterFormat division for general requirements: the administrative procedures for submittals, quality, meetings, temporary facilities, and closeout. It applies to every trade.

The general conditions are the legal terms of the contract. Division 01 is a specification division that sets project procedures. They should agree. The agreement says which governs if they do not.

It contains cost items that have no neat quantity: temporary facilities, mockups, coordination drawings, allowances, and closeout. Skipping it underprices the job.

At the front of the specifications, after the procurement documents and before the technical divisions.