What Is CSI MasterFormat?

Last reviewed: September 2026

MasterFormat is the Construction Specifications Institute system for organizing construction specifications into numbered divisions and sections. A six-digit section number such as 03 30 00 tells you the subject of that spec, and where to file a submittal that cites it.

Published by
CSI, the Construction Specifications Institute, with CSC in Canada
Numbering
50 divisions, six-digit section numbers
Division 00
Procurement and contracting requirements
Division 01
General requirements
Technical work
Divisions 02 through 48, by work result
Not the same as
UniFormat, which groups by elements for early estimates

Definition

CSI MasterFormat

Before MasterFormat, every firm invented its own spec order, and a submittal for paint could be anywhere. The current MasterFormat uses 50 division numbers, 00 through 49, and six-digit section numbers. Some numbers are reserved and unused. Division 00 holds procurement and contracting requirements. Division 01 holds general requirements that apply across trades. The other active divisions hold technical work results, from existing conditions and concrete through electrical and process equipment. Estimators, product reps, and contractors all use the same numbers, which is why a drawing note that cites "Section 09 91 00" can be checked. UniFormat is a different system, organized by building elements, and it is used more often for early estimates than for the project manual.

In depth

How to read a section number

The first pair of digits is the division. The next pairs narrow the work result. 03 is concrete. 03 30 00 is cast-in-place concrete. A level 4 number such as 03 30 53, miscellaneous cast-in-place concrete, is more specific still. You do not need to memorize the list to use a project manual. You need to know that the number on the submittal stamp should exist in the table of contents.

Within a section, the three-part format is the usual structure: Part 1 General, Part 2 Products, Part 3 Execution. Submittals, quality assurance, and warranties live in Part 1. The product the contractor wants to substitute is judged against Part 2. Installation and field quality control live in Part 3. A review that only reads the product name misses the execution requirements.

Division 01 governs the other divisions

Division 01 is where submittal procedures, substitution procedures, quality requirements, temporary facilities, and closeout requirements are written once. Technical sections then point back to them. A contractor who prices only Divisions 02 through 48 and treats Division 01 as boilerplate will miss cost. A reviewer who approves a submittal without the Division 01 submittal procedure will miss process.

General conditions of the contract, often AIA A201, are not Division 01. They are usually bound in Division 00 or incorporated by reference. Division 01 is the specifier’s administrative specifications. The general conditions are the contract’s legal machine. Both apply. They are written by different authors.

Where common work sits, so you can look it up

Concrete is Division 03, masonry 04, metals 05, wood 06, thermal and moisture protection 07, openings 08, finishes 09. Fire suppression is 21, plumbing 22, HVAC 23, electrical 26. Site work is in the 31 through 33 range: earthwork, exterior improvements, utilities. If a drawing says "see specs" with no number, MasterFormat at least tells you which division the requirement should have lived in.

Specifiers add project-specific sections and delete unused ones. A short project manual is not a violation. A project manual that invents a private numbering scheme, or that cites a section it does not contain, breaks the cross-references on the drawings. The drawing note and the section number have to match.

UniFormat is the other CSI language

UniFormat organizes information by elements and systems, such as substructure, shell, and services, which matches how early estimates and BIM assemblies are discussed. MasterFormat organizes by work results and products, which matches how the work is bought and installed. A DD estimate in UniFormat and a CD project manual in MasterFormat are supposed to describe the same building. They will not line up row for row.

Switching systems midstream without a crosswalk is how scope falls out of the estimate. If the owner’s cost report is in UniFormat and the spec is in MasterFormat, someone has to own the map. The numbers are standards. The map is a project decision.

Examples

CSI MasterFormat on a real project

  • 01

    A paint submittal is reviewed against Section 09 91 00 and the Division 01 submittal requirements.

  • 02

    A drawing note cites Section 03 30 00, and the project manual’s table of contents includes that section.

  • 03

    An early estimate organized in UniFormat is reconciled to MasterFormat sections when the project manual is written.

FAQ

Frequently asked questions

MasterFormat is CSI’s standard for organizing specifications and related construction information. It divides the project manual into numbered divisions and six-digit sections so every reader can find the same work result in the same place.

MasterFormat has 50 division numbers, 00 through 49. Some numbers are reserved and not used. Division 00 is procurement and contracting requirements, Division 01 is general requirements, and the active technical divisions cover work such as concrete in 03 and electrical in 26. Not every project uses every division.

MasterFormat organizes specifications by work results and products, which is how project manuals and submittals are filed. UniFormat organizes information by building elements and systems, which fits early cost estimates. They describe the same project in different structures.

Division 01 is General Requirements. It covers administrative rules that apply across trades, such as submittal procedures, quality requirements, and closeout. Technical sections rely on it instead of repeating those rules in every section.
Accelerating the design and construction of the built world.

Unlock the value of your institutional knowledge—organized, connected, and grounded in your team's critical workflows with Nomic.

Start for free
What Is CSI MasterFormat? Specification Numbers Explained | Nomic