What Does “No Exceptions Taken” Mean on a Submittal?

Last reviewed: November 2026

No exceptions taken is the review action a design professional stamps on a submittal when the review found nothing that conflicts with the contract documents. It is not a blanket approval. The contractor stays responsible for the work and for any deviation not specifically flagged.

What it means
The reviewer found no conflict with the contract documents
What it is not
Approval of a deviation or a release from the contract
Who stamps it
The architect or engineer responsible for that part of the design
Next step
The contractor can order, fabricate, or install
Neighboring actions
Exceptions noted, revise and resubmit, rejected
Wording defined in
The specification’s submittal procedures, often Division 01

Definition

No Exceptions Taken

When a contractor sends a shop drawing, product data sheet, or sample to the architect or engineer, the reviewer returns it with a review action. No exceptions taken is the most favorable one: the reviewer looked at it for conformance with the design concept and the information in the contract documents and found nothing to correct. The standard wording differs between firms and projects, and the specification’s submittal procedures usually define the set of actions, which commonly run from no exceptions taken to exceptions noted, revise and resubmit, and rejected. The action tells the contractor what to do next. It does not change the contract.

In depth

What the stamp tells the contractor

No exceptions taken tells the contractor that the reviewer, within the limited scope of the review, found no conflict between the submittal and the contract documents. The contractor can release the item for fabrication or delivery. It does not tell the contractor that the dimensions are right, that the product coordinates with its neighbors, or that the reviewer checked every line.

Under the AIA A201 general conditions, the contractor represents that it has reviewed and coordinated the submittal before sending it, and the architect’s review is only for conformance with the design concept and the information in the contract documents. The review is a second set of eyes. It does not take over the contractor’s duty to check the work.

The other review actions and what each one triggers

Exceptions noted, or make corrections noted, means the item can proceed once the contractor makes the changes the reviewer marked. A resubmittal is usually not required. Revise and resubmit means the item cannot proceed. The contractor corrects it and sends a new submittal, and the clock on the schedule keeps running. Rejected means the submittal does not meet the documents and a different product or approach is needed.

Some projects add actions such as no review required, for items the specification lists as informational, or furnish as corrected. The names are not universal. Read the project’s Division 01 submittal procedures before assuming what a stamp commits anyone to.

A deviation is not approved by a clean stamp

If the submittal differs from what the contract documents require, the contractor has to call that out in writing when it submits. Under A201 section 3.12.8, a reviewer’s approval does not relieve the contractor of responsibility for a deviation unless the contractor specifically notified the architect at the time of submittal and the architect approved the deviation in writing, or a change order or construction change directive authorized it.

That is why no exceptions taken on a substitution that was buried in a product data sheet is a real risk. The stamp confirms the reviewer saw nothing, not that the reviewer approved a change. A contractor who wants a substitution accepted should say so on the transmittal.

Where review actions go wrong in practice

The common failures are quiet. A reviewer stamps the cover sheet and the notes inside contradict the specification. A resubmittal returns with changes beyond the ones requested, and the A201 says the architect’s approval of a resubmission does not apply to revisions the contractor did not call out. A stamp is dated but the log never updates, so the superintendent orders against an old status.

Each of these is a documentation gap rather than a judgment gap. The submittal log, the stamped file, and the transmittal need to agree on the current status of every item, because the field will act on whichever one it sees first.

Examples

No Exceptions Taken on a real project

  • 01

    A door hardware submittal comes back no exceptions taken, and the contractor releases the order to the supplier.

  • 02

    A pump submittal comes back exceptions noted with a request to correct the motor voltage, and the supplier proceeds once the correction is made.

  • 03

    A curtain wall shop drawing comes back revise and resubmit because the anchor spacing conflicts with the structural drawings.

Tooling

Where AI helps with submittal review actions

A reviewer deciding between no exceptions taken and exceptions noted is comparing a submittal against the specification section, the drawings, and any earlier comments. That comparison is the slow part, and the one that benefits from a cited second read.

Nomic compares a submittal with the governing specification and drawings and cites the clause or sheet for each difference it finds. The review action stays with the design professional whose name is on the stamp.

Compare AI tools for submittal review

Best AI for Submittal Review in 2026

FAQ

Frequently asked questions

It means the reviewer found nothing in the submittal that conflicts with the contract documents, within the limited scope of the review. The contractor can proceed, and remains responsible for the work and for any deviation it did not specifically flag.

Not exactly. Some projects use the word approved. No exceptions taken is the more careful phrasing, because the architect’s review is limited to conformance with the design concept and the contract documents. It does not release the contractor from the contract requirements.

Exceptions noted means the contractor can proceed after making the marked corrections. Revise and resubmit means the contractor cannot proceed until it corrects the submittal and sends a new one for review.

The specification’s submittal procedures, usually in Division 01, define the actions and what each one requires. The wording varies by firm and by project, so read the project’s own definitions.