An RFI is a contractual instrument, not a message
That distinction explains almost everything about how an RFI behaves on a project. Because the response becomes part of the contract record, it has to be written, numbered, dated, and routed through a defined chain — contractor to construction manager to architect, often out to a consultant, and back again.
A question that would take thirty seconds to answer verbally takes a week to answer formally, and the week is the point: the written answer is what protects both parties if the work later turns out to be wrong. Verbal direction on a job site is not a substitute, and experienced teams treat it as a prompt to raise an RFI rather than as an answer.