AEC definitions

What Is a Subcontractor?

Last reviewed: September 2026

A subcontractor is a firm the prime contractor hires to perform part of the work under the prime contract. The subcontractor's contract is with the prime, not the owner. Flow-down clauses pass schedule, safety, and document duties to the sub. Suppliers who only deliver materials are not subcontractors, and the difference matters for bonds and liens.

Contract with
The prime contractor, or a higher-tier sub
Not with
The owner, unless it is a separate prime
Performs
A defined portion of the work, with labor
Prime remains
Responsible to the owner for that work
Unlike a supplier
A supplier sells materials without installing them
Paid through
The prime, subject to the subcontract

Definition

Subcontractor

The general contractor remains responsible to the owner for the subcontractor's work. The owner does not direct the sub's crew, except through the prime, unless the contracts say otherwise. A sub-subcontractor is hired by a subcontractor. Payment follows the chain: owner to prime to sub, which is why pay-if-paid and pay-when-paid clauses are negotiated, and why lien and bond rights exist. The subcontract should incorporate the drawings, specifications, and the scope sheet that was leveled. A one-line purchase of 'electrical' is how exclusions reappear.

In depth

The subcontract is the scope

Attach the trade package, the relevant spec sections, the schedule, and the flow-down. Exclusions accepted at bid leveling should be written in. Exclusions that were rejected should be gone.

Separate primes, used on some public jobs, contract directly with the owner. They are not subcontractors of each other, and someone still has to coordinate them. The owner often holds that risk.

Who can tell the crew what to do

The superintendent directs means and methods inside the contract. The architect does not direct the subcontractor's labor. An architect who does can create a claim and a safety problem.

Design questions go up as RFIs. Field coordination among subs is the prime's job.

Payment terms are a risk clause

Pay-when-paid ties timing to the owner's payment but may still require the prime to pay eventually. Pay-if-paid, where enforceable, shifts the owner's nonpayment risk to the sub. Many states limit those clauses. Know which sentence is in the subcontract.

Lien waivers travel with each payment. Retainage should match the prime contract's retainage, or the prime will finance the difference.

Safety flows down

The prime's safety plan applies. A sub who arrives without orientations, competent persons, or the required insurance can be removed. Removal does not delete their scope. It means someone else performs it, sometimes by back charge.

Multi-employer sites still have individual duties. Flow-down does not erase a sub's own safety obligations.

The prime can complete the work

Subcontract default clauses allow the prime to supplement or replace a crew that falls behind, after notice, and to back-charge the cost.

The clause is not a license to starve a sub of information and then declare default.

Examples

Subcontractor on a real project

  • 01

    The mechanical subcontractor signs a subcontract that incorporates the mechanical drawings, Division 23, and the leveled scope sheet.

  • 02

    A supplier drops off fixtures and does not install them. They are a supplier. The installing firm is the subcontractor.

  • 03

    The owner asks a subcontractor's foreman to move a wall. The foreman sends the request through the superintendent so the prime can price it.

FAQ

Frequently asked questions

A firm hired by the prime contractor to perform part of the construction work. The subcontract is with the prime. The prime remains responsible to the owner.

A subcontractor performs work, usually with labor on site. A supplier furnishes materials or equipment without installing them. Bonds, liens, and safety rules often treat them differently.

The prime contractor, under the subcontract. The owner's payment to the prime is a separate contract. Clauses may tie the timing or, where enforceable, the duty to pay.

The contract path is through the prime contractor. Direct orders from the owner or architect can create scope and safety problems and should be put in writing through the prime.