A lien waiver is a document in which a contractor, subcontractor, or supplier gives up the right to file a lien for the amount of work the waiver covers, in exchange for payment. A conditional waiver is effective when the payment clears. An unconditional waiver is effective when it is signed, so it should not be signed before the money is in hand.

Given by
The party who would have lien rights
Conditional
Effective only if the payment is received
Unconditional
Effective on signature
Partial
Covers one period or one amount
Final
Covers the remaining rights on that scope
Watch
Through dates, retainage, and pending changes

Definition

Lien waiver

Owners and lenders collect waivers so they are not paying the prime contractor while a subcontractor preserves a lien. Partial waivers cover a payment period. Final waivers cover the rest of the work. The form should state the through date and the amount, and it should reserve rights for retainage and unresolved changes if those are not being paid. Many states specify the form. A waiver that releases more than the check, or that a state form does not allow, creates a different deal than the parties thought. This is a payment document. It is not a determination that the work is defect-free, unless the form says that too.

In depth

Use conditional waivers before the check clears

The safe exchange is a conditional waiver with the pay application, and an unconditional waiver next month for the payment that cleared. Signing an unconditional waiver against a promised payment leaves the signer unsecured if the check fails.

The condition should name the amount and the payer. A waiver conditioned on 'payment' with no amount is sloppy.

The date is the scope of the release

Work performed after the through date is not waived. Work before it is. A through date that runs past the payment, or that includes unapproved changes, releases claims the check did not buy.

Retainage should be excluded in writing until it is paid. A final waiver that forgets retainage arguments is a common surprise.

Collect them down the chain

A waiver from the prime does not waive the subcontractor's rights. Owners require waivers from subs and suppliers for the amounts the prime says it paid them. False statements about those payments are a separate problem.

Lower-tier waivers should match the amounts the prime's payment breakdown claims.

Use the form the state requires

Some states mandate statutory waiver forms and limit what extra language can do. A custom form pulled from another state can be void or can waive more than intended. Counsel picks the form. The project team uses it consistently.

Notarization, if required, is part of the form, not a courtesy.

A payment waiver is not acceptance of bad work

Unless the document clearly releases warranty and defect claims, a lien waiver releases lien rights for the dollars stated.

Quality claims travel under the warranty and the contract. Do not assume one signature did both. Do not hide a claim release in a lien form without saying so.

Examples

Lien waiver on a real project

  • 01

    A subcontractor signs a conditional partial waiver for a progress payment. The waiver becomes effective when that payment clears.

  • 02

    The final waiver excludes retainage by amount and excludes a pending change the owner has not approved.

  • 03

    The owner rejects an unconditional waiver signed before funds were received and asks for the conditional form instead.

FAQ

Frequently asked questions

It is a signed release of the right to file a mechanic's lien for the payment and period the document describes.

A conditional waiver takes effect when payment is received. An unconditional waiver takes effect when signed, even if the check later fails.

It releases the remaining lien rights on the scope, usually at the last payment. It should be explicit about retainage and unresolved claims if those are meant to survive.

Not by itself. It waives lien rights for the sums stated. Warranty and defect claims remain unless the document clearly releases them too.