AEC definitions

What Is a Pay Application in Construction?

Last reviewed: September 2026

A pay application, or pay app, is the contractor’s formal request for a progress payment. It bills a percentage complete against each line of the schedule of values, minus retainage and previous payments, for a defined period.

Also called
Pay app, application for payment, progress billing
Common AIA forms
G702 cover and G703 continuation sheet
Measured against
The approved schedule of values
Typical cycle
Monthly, on a date the contract names
Often withheld
Retainage, commonly five or ten percent
Submitted with
Lien waivers and, when required, backup from subcontractors

Definition

Pay Application

On AIA contracts the package is G702, the Application and Certificate for Payment, and G703, the continuation sheet that lists the schedule of values. The contractor states work in place and materials stored, the architect or owner’s representative reviews it against the site, and the architect certifies an amount when the contract gives them that role. The owner then pays the certified amount, usually withholding retainage. A pay app is not an invoice in the casual sense. It is a sworn statement of progress, often accompanied by lien waivers, and overbilling it is a contract problem, not a paperwork quibble.

In depth

The math is percent complete, not a round number

Each schedule-of-values line has a scheduled amount. The contractor enters percent complete or dollar complete for the period, plus stored materials if the contract allows them. Previous certificates are subtracted. Retainage is calculated on the amount earned. The current payment due is what is left. Front-loading, putting too much money on early activities such as mobilization, is visible on this sheet if the original schedule of values was reviewed.

Stored materials need evidence: invoices, insurance, and sometimes photos or a bill of sale, stored on site or in a bonded warehouse. Billing steel that is still at the mill is not stored material. The continuation sheet has a column for this because it is a frequent argument.

Who reviews it, and what they are checking

The contractor’s project manager prepares the draft, often after a pencil copy meeting with the owner’s rep or the architect so percentages are argued before the formal submittal. The architect, when required by the owner-architect agreement, walks the job and certifies an amount. Certification is not a guarantee that the work complies with the documents. AIA language is careful about that. It is a representation that, to the best of the architect’s knowledge and observation, the work has progressed to the point indicated.

Reviewers look for overstated percents, lines with no work in place, change orders that are billed before they are signed, and retainage calculated on the wrong base. Subcontractor backup should roll up to the prime’s lines. A prime application that cannot be tied to trade invoices is not ready to certify.

Lien waivers travel with the payment

Owners require conditional lien waivers with the application and unconditional waivers after the check clears, from the prime and often from subcontractors and suppliers. The waiver should match the amount and the through date. A waiver that is broader than the payment, or that arrives unsigned, holds the certificate.

State lien law changes the forms and the deadlines. The pay app process does not. Someone on the owner’s side matches waiver, application, and check every month, or retainage release at the end becomes a forensic project.

Change orders and retainage have to hit the same sheet

Approved change orders add lines or adjust existing ones. Billing a construction change directive as if it were approved original scope overstates the contract sum. Until the change order is executed, many contracts allow billing only to the extent the architect has included it in a certificate, and even that is contract-specific. Read the payment article before you add the column.

Retainage is released on the schedule the contract states, often partially at substantial completion and the rest at final payment. The pay app at substantial completion is a different animal from a monthly app: punch list, warranties, and consent of surety show up as conditions. Treating it as "month 18, same form" is how final payment stalls.

Examples

Pay Application on a real project

  • 01

    A general contractor submits a G702/G703 through the 31st, billing drywall at 40 percent and withholding ten percent retainage.

  • 02

    The architect reduces a concrete line after the site walk shows the deck is not placed.

  • 03

    Stored switchgear is billed only after the contractor attaches the invoice and insurance certificate.

FAQ

Frequently asked questions

A pay app is an application for payment. The contractor requests a progress payment for work in place during a period, based on the schedule of values, less retainage and amounts already paid.

G702 is the cover sheet: the application and, when used, the architect’s certificate. G703 is the continuation sheet that itemizes the schedule of values, percent complete, stored materials, retainage, and the amount due.

The contractor submits it. The architect often certifies the amount when the owner-architect agreement includes that service. The owner pays. Certification is based on observation and the documents, and it is not a promise that every detail complies.

Retainage is a percentage withheld from the amount earned, often five or ten percent, until substantial completion or final completion. The pay application shows retainage held to date and the current amount withheld.
Accelerating the design and construction of the built world.

Unlock the value of your institutional knowledge—organized, connected, and grounded in your team's critical workflows with Nomic.

Start for free
What Is a Pay Application? Construction Billing Explained | Nomic