AEC definitions

What Is a Schedule of Values?

Last reviewed: September 2026

A schedule of values, or SOV, is a breakdown of the contract sum into line items the project will use to measure progress payments. The owner or architect approves it before the first pay application, and every later pay app bills against those same lines.

Stands for
Schedule of values
Allocated amount
The full contract sum, including fee if it is a line
Approved before
The first application for payment
Used on
Every progress payment, typically AIA G703
Common abuse
Front-loading early or general lines
Updated by
Approved change orders, as new or revised lines

Definition

Schedule of Values (SOV)

The contract sum is one number. Cash flow and oversight need more detail than that. The SOV splits the sum into activities or systems, mobilization, general conditions, concrete, steel, each trade, often with a line for the contractor’s fee. AIA G703 uses this breakdown as the rows of the pay application. A fair SOV allocates money in proportion to cost. A front-loaded SOV puts too much money on early, vague lines so the contractor is paid ahead of work in place. Approving the SOV is the owner’s main chance to prevent that.

In depth

The breakdown has to be buildable and billable

Lines that are too coarse, "MEP, one lump," make percent-complete a guess and hide which trade is overbilled. Lines that match the contractor’s cost codes, or the specification divisions that carry real money, can be walked in the field. Division 01 costs, general conditions, supervision, temporary facilities, need their own lines so they are not buried in a trade.

The specification is a useful cross-check. If Division 03 is a large share of the drawings and a small share of the SOV, the money is sitting somewhere else, often in an early line. Owners ask for the SOV far enough before the first billing to send it back.

Front-loading shows up if you look at the early lines

Mobilization, submittals, and general conditions are real costs, and they are also the easiest place to park profit. A mobilization line that is several percent of a hard-bid building, with no schedule of what it buys, deserves a question. So does a "project management" line that would be fully billed by month three of an eighteen-month job.

Unit-price and GMP contracts need the same scrutiny for different reasons. On a GMP, the SOV should tie to the estimate the GMP was built from, including contingencies that are not yet scope. Billing contingency as if it were work in place spends the owner’s risk money early.

Approval is a commercial decision, not a stamp

The contract usually says the contractor submits the SOV promptly and the architect or owner approves it. Approval means the breakdown is a reasonable basis for payment, not that every line equals the subcontractor’s private buyout. The contractor’s buyout and fee allocation can stay commercially sensitive. The owner still needs enough detail to certify progress.

Rejecting an SOV delays the first payment, so it should be done with specific comments: split this line, reduce mobilization, add stored-material rules. Silence plus a paid first pay app is approval in practice, even if nobody signed a form.

The SOV has to absorb changes without becoming fiction

Each change order adds value that must land on a line. Folding changes into original lines makes "percent complete" unreadable, because the denominator moved quietly. New lines labeled with the change-order number keep original scope and changed scope auditable.

At substantial completion the SOV should reconcile: work in place, retainage, punch remaining, and unsettled changes. A schedule of values that nobody updated since month two cannot support a final payment recommendation. The continuation sheet is the project’s financial as-built.

Examples

Schedule of Values (SOV) on a real project

  • 01

    An owner sends back an SOV that bills 80 percent of general conditions in the first quarter of a year-long job.

  • 02

    Concrete, steel, and each MEP trade are separate lines so the site walk can test the percent complete.

  • 03

    Change Order 5 is added as its own SOV line instead of being buried in the original finishes line.

FAQ

Frequently asked questions

SOV means schedule of values. It itemizes the contract sum so progress payments can be calculated line by line. The contractor proposes it, and the owner or architect approves it before the first pay application.

The schedule of values is the breakdown of the contract sum. The pay application is the periodic bill that reports how complete each of those lines is. The SOV is the rows. The pay app fills in the progress.

Front-loading assigns too much of the contract sum to early activities, so the contractor is paid ahead of the work in place. Owners review mobilization, general conditions, and other early lines before approving the SOV.

Usually before the first application for payment, on a deadline the contract states. It should be approved in writing. Later change orders revise it. The original lines should not be quietly rewritten.
Accelerating the design and construction of the built world.

Unlock the value of your institutional knowledge—organized, connected, and grounded in your team's critical workflows with Nomic.

Start for free
What Is a Schedule of Values in Construction? | Nomic