AEC definitions

What Is Retainage in Construction?

Last reviewed: September 2026

Retainage is a percentage of each progress payment that the owner withholds until the contractor finishes the work. It gives the owner security for punch, closeout, and correction. Five or ten percent is common, and many states cap the rate or the period.

Also called
Retention
Typical rate
Five or ten percent, subject to the contract and state law
Withheld from
Progress payments, shown on the pay application
Often reduced at
Substantial completion
Released at
Final completion, sometimes with surety consent
Not the same as
Liquidated damages or a backcharge

Definition

Retainage

On each pay application the contractor earns an amount for work in place. Retainage, also called retention, is the portion the owner does not pay yet. It accrues across the job and is released according to the contract, often in part at substantial completion and the balance at final payment. The general contractor usually withholds retainage from subcontractors on the same logic. It is not a penalty and it is not liquidated damages. It is held contract money. Billing that ignores it overstates cash due. Waiving it informally, without a contract change, gives up the security the bid assumed.

In depth

It is security, held in the open

Owners withhold retainage so a contractor who has been paid for nearly all the work still has a reason to finish the punch list, deliver O&M manuals, and correct defective work. The amount is visible on every pay application: retainage to date, retainage this period. Subcontractors watch it because their retainage is often stuck until the prime’s retainage moves.

The rate is a commercial term. Ten percent on a long job is a large receivable. Five percent is common on public work because statutes say so. Some contracts drop from ten to five after the job is half complete. If you do not read the payment article, you will forecast cash from the wrong percentage.

Release is staged, and it is not automatic

At substantial completion many contracts release retainage except an amount the architect sets to cover incomplete work, often something above the estimated punch cost. The rest waits for final payment, consent of surety if the contract requires it, and final lien waivers. "Substantially complete" on a certificate does not wire the retainage the same day.

Subcontractor retainage follows the subcontract, which may say the sub is paid retainage when the owner pays the prime, not when the sub’s own work finished. That pay-if-paid or pay-when-paid language is heavily litigated and sometimes limited by statute. The prime’s schedule of values will not explain it. The subcontract will.

Where people miscalculate it

Retainage usually applies to work in place and may or may not apply to stored materials, depending on the contract. Change orders are generally subject to the same rate once they are in the contract sum. Calculating retainage on the original contract only, after large change orders, under-withholds. Calculating it on a line the contract exempts, such as insurance or a bond, over-withholds.

A pay application that "rounds" retainage will not match the next one. The continuation sheet should carry the balance forward. Reconstructing retainage from bank deposits at closeout is a sign the sheet was not trusted during the job.

Retainage is sometimes substituted, not deleted

Some contracts allow a retainage bond or a letter of credit in lieu of cash withholding, more often late in the job or on large subcontracts. The owner still has security. The form of security changed. That substitution should be written. A handshake that "we’ll stop holding five percent" is a modification of the payment clause.

Owners who withhold extra money beyond contractual retainage, as unstructured leverage, create a different dispute: wrongful withholding. Retainage is the authorized hold. Backcharges and disputed change orders need their own documentation. Piling them into the retainage line hides all three.

Examples

Retainage on a real project

  • 01

    A pay application earns $100,000 and withholds five percent, so the current payment due is reduced by $5,000.

  • 02

    At substantial completion the owner releases retainage except for 200 percent of the estimated punch cost.

  • 03

    A state statute caps retainage at five percent, and the contract’s ten percent clause has to yield.

FAQ

Frequently asked questions

Retainage is money the owner withholds from the contractor’s progress payments, usually a percentage of the amount earned, until the work reaches substantial or final completion. It secures completion and correction of the work.

Five or ten percent is common. Public projects often follow a state statute that sets a cap. Some contracts reduce the rate after a midpoint. The contract and applicable law control, not a rule of thumb.

Often in part at substantial completion, with a holdback for punch and closeout, and the balance at final payment. Subcontractor release may wait until the owner pays the general contractor, if the subcontract says so.

No. Retainage is a portion of earned contract money held back temporarily. Liquidated damages are a contractual charge for late completion. They are calculated and documented separately.
Accelerating the design and construction of the built world.

Unlock the value of your institutional knowledge—organized, connected, and grounded in your team's critical workflows with Nomic.

Start for free
What Is Retainage in Construction? Held Payments Explained | Nomic