Substantial completion and final completion
Substantial completion is the more consequential of the two, because so much attaches to the date. The owner can occupy. Warranty periods begin. Liquidated damages stop accruing. Responsibility for insurance, security and utilities shifts. Retainage is often partially released. Establishing the date therefore matters commercially, and it is negotiated more often than the contract language suggests it should be.
Final completion is administrative but not trivial. It requires every punch list item closed and every required submittal delivered and accepted, and it releases the remaining money. Projects commonly reach substantial completion on schedule and then take months to reach final completion, which is almost always a documentation problem rather than a construction one.