What Is Schematic Design?

Last reviewed: September 2026

Schematic design, often called SD, is the first design phase after programming. It establishes the building’s arrangement, scale, structural concept, and code strategy with drawings that are still diagrammatic enough to change.

Abbreviation
SD
Comes after
Programming, or the owner’s approved requirements
Comes before
Design development (DD)
Drawings look like
Plans, massing, and key sections, still open to change
Cost document
A preliminary estimate with contingency
Owner’s decision
Approve the scheme before DD starts

Definition

Schematic Design (SD)

AIA agreements describe schematic design as the phase where the architect prepares documents that illustrate the scale and relationship of project components. In practice that means plans, massing, and a narrative or outline of systems, plus a preliminary cost. The owner approves the scheme before design development spends fee on details that assume the plan is settled. Owners who use percent-complete submissions sometimes map the end of schematic design to a 30% design package. That mapping is contractual, not automatic. A 30% construction document set on a building project is later than SD.

In depth

The decisions schematic design is for

SD settles the moves that are expensive to reverse: where the building sits, how tall it is, where people enter, where the stairs and elevators land, and which structural system can span the bays. Code work at this phase is a strategy, not a full analysis: occupancy, construction type, and whether the exiting concept works. Mechanical and electrical concepts are described, not routed sheet by sheet.

What SD does not do is pick every finish, size every beam, or write a project manual. Teams that draw SD to CD resolution spend the fee early and then defend details the owner has not approved. The drawings should be clear enough to estimate and to reject a bad scheme, and loose enough that a stair can still move.

Deliverables an owner should actually receive

A typical SD package includes a site plan, floor plans, major elevations, a couple of sections, a narrative of structural and MEP systems, a code summary, and an estimate. Some contracts add a simple model or renderings so a non-technical owner can see the massing. The owner-architect agreement lists the actual deliverables. A firm’s internal SD checklist is not the contract.

Outline specifications sometimes start here as a system list: steel frame, curtain wall, packaged rooftop units. That list is what the estimator prices. If a system is missing from the narrative, it is missing from the cost, and it will look like growth in design development.

Why the owner’s approval is the real deliverable

Design development assumes the SD scheme. Consultants size equipment, the structural grid hardens, and the fee burn rate jumps. An owner who "approves SD" while still debating the program will pay for that debate in redrawn DD documents. Written approval, with the estimate attached, is what lets the architect proceed.

Comments at SD should attack the scheme: the core is too far from the lease span, the loading dock conflicts with the zoning setback, the construction type will not allow the height. Annotation comments can wait. There is not enough drawing yet to annotate.

How SD lines up with 30% submissions

Agencies that never say "schematic design" still have an early gate. A 30% design submission on a federal or DOT job is often that gate: criteria, general arrangement, typical sections, preliminary cost. Calling it a 30% CD confuses the builder’s reviewers, who expect construction documents.

Fast-track and design-build jobs overlap SD with procurement of long-lead items. The overlap does not delete the phase. Someone still has to approve the arrangement before steel is released, or the early package becomes the first change order.

Examples

Schematic Design (SD) on a real project

  • 01

    An SD floor plan shows the structural grid and exit stairs, without door numbers or a finish schedule.

  • 02

    An owner rejects an SD scheme because the estimate exceeds the budget while the plan can still change.

  • 03

    A civil 30% design submission plays the role SD plays on a building, under a different name.

FAQ

Frequently asked questions

Schematic design is the phase that establishes the scale and arrangement of the project: plans, massing, a structural and systems concept, a code strategy, and a preliminary cost. The owner approves it before design development.

Schematic design chooses the scheme. Design development develops that scheme: system sizes, materials, outline specifications, and dimensioned plans. SD can still move a stair. DD is pricing and coordinating the stair that stayed.

Usually a site plan, floor plans, major elevations and sections, and a narrative of building systems, plus a preliminary estimate. The owner-architect agreement lists the exact deliverables.

Only when the contract says so. Many civil and federal projects use a 30% design submission where architects would say schematic design. A 30% CD on a building project is a later construction-document milestone.
Accelerating the design and construction of the built world.

Unlock the value of your institutional knowledge—organized, connected, and grounded in your team's critical workflows with Nomic.

Start for free
What Is Schematic Design? The SD Phase Explained | Nomic