What Is Design Development?

Last reviewed: September 2026

Design development, or DD, is the phase that develops an approved schematic design into sized systems, selected materials, and outline specifications. It fixes enough of the building that construction documents can be drawn without reopening the scheme.

Abbreviation
DD
Comes after
Approved schematic design
Comes before
Construction documents (CD)
Specs at this phase
Outline specifications, not a full project manual
Main risk
Entering CDs with systems still undecided
Owner’s decision
Approve materials, systems, and the updated cost

Definition

Design Development (DD)

If schematic design asks "what is the building," design development asks "what is it made of, and does it fit." Structural members get sizes, mechanical equipment gets capacities and rooms, electrical service is estimated, and the envelope is drawn as assemblies rather than as a rendering. Outline specifications describe products and performance well enough for a real estimate. The owner’s approval at the end of DD is approval of those choices. Construction documents then turn them into coordinated, enforceable sheets. Teams that enter CDs with open DD decisions draw the same wall three times.

In depth

Systems get sized, not just described

A schematic narrative can say "steel frame and rooftop units." DD has to show the bay size, a plausible member depth, the unit capacity, and the room that holds the unit, with structure and architecture agreeing on the floor-to-floor height. Mechanical, electrical, and plumbing mains are routed far enough to prove the ceiling and the shafts work. Fire protection criteria are stated.

This is also when consultant coordination starts to cost real hours. An architect who finishes DD plans without the structural grid from the engineer does not have a DD set. The phase is interdisciplinary by nature. A single-discipline package labeled DD is a progress print.

Outline specifications are the cost document

Outline specs list systems, performance, and often a basis of design product, without the full three-part section a project manual needs. Estimators use them to stop pricing "mechanical, lump sum." If the outline says variable air volume and the estimate assumed packaged units, the gap is visible now, while the equipment can still change.

Product selections in the outline become the argument later, during submittals. A basis of design named in DD and then silently swapped in CDs creates a specification the estimate never saw. Write the substitution down when it happens.

DD is not a sloppy set of construction documents

Construction documents add the coordination, details, schedules, and general conditions that a contractor can bid and a building department can review. DD drawings are dimensioned and serious, and they still omit conditions a CD set must show. Expecting bid-day completeness at DD either inflates the fee or produces a CD set that is only a cleaned-up DD set, which bidders will punish with RFIs.

Owners who call late DD "60% CDs" should say so in the contract and attach a sheet list. The nickname does not change the standard of what a bidder is entitled to. Percent labels and AIA phase names need one crosswalk, written once.

The approval should include the cost

DD approval without an updated estimate is how projects discover the budget problem during CDs, after details are drawn. The estimate at DD is the one that should trigger value engineering. Cuts made here can be drawn once. Cuts made after the project manual is written have to be chased through every section.

The architect should not start full CD production on verbal approval. DD comments that reopen the structural system or the exterior wall are SD decisions arriving late. They belong in a formal change to scope before the CD fee is spent.

Examples

Design Development (DD) on a real project

  • 01

    A DD package sizes the air handlers and draws the shafts they need, with outline specs naming the system type.

  • 02

    An owner approves DD with a value-engineering list that deletes a facade system before details are drawn.

  • 03

    A project that starts CDs with the mechanical system still undecided redraws the ceiling coordination twice.

FAQ

Frequently asked questions

The design team develops the approved schematic design: member and equipment sizes, materials and assemblies, dimensioned plans, and outline specifications, plus an updated cost. The owner approves those decisions before construction documents.

Design development decides the systems and materials. Construction documents draw and specify them completely enough to permit, bid, and build. DD can still adjust a shaft. CDs coordinate the shaft that was kept.

Outline specifications are abbreviated spec descriptions used in design development to identify systems, performance, and often a basis of design. They are not the project manual issued for bid.

Complete enough to size, estimate, and coordinate major systems, and incomplete relative to a bid set. Details, full schedules, and a three-part project manual are construction document work.
Accelerating the design and construction of the built world.

Unlock the value of your institutional knowledge—organized, connected, and grounded in your team's critical workflows with Nomic.

Start for free
What Is Design Development? The DD Phase Explained | Nomic