Sixty percent is a coordination gate
At 30 percent a reviewer can forgive a duct main drawn as a single line. At 60 percent that main should have a size, a route, and a ceiling zone, because the architect is drawing the reflected ceiling and the structure is placing beams. This is the submission where an overlay of architectural, structural, and MEP plans earns its time. If the team is still moving the core, the set is behind the label.
Federal and DOT "60% design" packages follow the same idea with their own checklists: design analysis further along, more plan sheets, draft specifications, and an updated estimate. The percentage is the contract’s percentage. A building 60% CD and a roadway 60% design both deserve a coordination review, and they do not contain the same sheets.