What Is a 60% CD?

Last reviewed: September 2026

A 60% CD is a construction document set about 60 percent complete. Most plans are drawn, major systems are sized, and specifications are in draft, so disciplines can coordinate before details and the project manual lock in at 90 percent.

Stands for
60 percent construction documents
Comes after
30% CD, or 30% design on the same percentage scale
Main purpose
Interdisciplinary coordination and a credible cost check
Specs at this gate
Draft sections, not a finished project manual
Who struggles here
MEP and structure, where routes and depths collide
Next gate
90% CD, the last review before the issued set

Definition

60% CD (60 Percent Construction Documents)

Sixty percent is the milestone where a drawing set stops being a description of intent and starts being checkable across trades. Architectural plans should be dimensioned, structural members sized, and mechanical, electrical, and plumbing mains routed far enough that clashes and shaft conflicts show up. Specifications exist as edited sections rather than an outline, even if product data and execution articles are still thin. Owners use this gate for a real cost check and for constructability comments that can still be drawn in. Comments that wait until 90 percent become change paper during bidding.

In depth

Sixty percent is a coordination gate

At 30 percent a reviewer can forgive a duct main drawn as a single line. At 60 percent that main should have a size, a route, and a ceiling zone, because the architect is drawing the reflected ceiling and the structure is placing beams. This is the submission where an overlay of architectural, structural, and MEP plans earns its time. If the team is still moving the core, the set is behind the label.

Federal and DOT "60% design" packages follow the same idea with their own checklists: design analysis further along, more plan sheets, draft specifications, and an updated estimate. The percentage is the contract’s percentage. A building 60% CD and a roadway 60% design both deserve a coordination review, and they do not contain the same sheets.

What should be drawn, and what can wait

Plans, major elevations, building sections, and the primary wall sections should be underway with real dimensions. Door and room schedules are often started, not finished. Typical details for structure and envelope are drawn. Unusual conditions may still be keyed as "detail later" if the plan location is settled. The code sheet should show occupancy, construction type, and exiting with numbers, not placeholders.

Specifications should name the section list and carry edited Part 2 products for the systems that drive cost: structure, envelope, HVAC, electrical distribution. Part 3 execution and the long tail of Division 10 specialties can still be thin. A 60% project manual that is still an outline spec from design development is not a 60% CD.

The last reasonable moment for cost moves

Estimators can quantity a 60% set. That is new. At 30 percent they were still applying allowances and unit rates to diagrams. A 60% estimate that jumps usually means either the 30% set hid scope or the design grew. Value engineering belongs in this review, while details are still uncoordinated and product lists are not printed in the spec.

Cutting scope at 90 percent leaves stranded details and specification sections that no longer match the plans. Owners who want a price correction should demand it with the 60% comment log, with each cut traced to a sheet and a spec section so the 90% set is internally consistent.

Comments that help, and comments that clog the log

Helpful 60% comments name a conflict: the beam and the duct occupy the same zone in the corridor, the door schedule width does not match the plan, the spec section calls for a roof the details do not draw. Each one can be fixed once and checked at 90.

A log full of spelling, title-block, and "add more dimensions" notes burns the review and hides the coordination misses. Those notes matter at 90 percent, when the set is about to be sealed. At 60, the question is whether the building as drawn can be built without a redraw.

Examples

60% CD (60 Percent Construction Documents) on a real project

  • 01

    A 60% CD review catches a duct main running through a steel beam because both trades have sized their work.

  • 02

    An estimator prices the envelope from draft specification sections instead of from an outline allowance.

  • 03

    An agency 60% design comment requires the drainage design to match the typical sections before the 90% plan sheets are produced.

FAQ

Frequently asked questions

Most architectural, structural, and MEP plans are drawn and dimensioned, primary sections and typical details are started, and specifications are in draft. Schedules and the full project manual are usually still incomplete. The owner’s submission requirements control the exact list.

Design development resolves systems and materials and usually ends with outline specifications. A 60% CD set is already inside construction documents: plans are meant to be coordinated, and specifications are being edited as contract sections. Some owners loosely call late design development "60%," which is why the contract language matters.

It is late enough to see real conflicts and early enough to change them in the drawings. The same comment at 90% often becomes a bidder question or a change order.

The owner reviews the submission, often with a construction manager and estimators. The architect or engineer of record collects comments, coordinates the consultants, and incorporates the accepted ones into the 90% set.
Accelerating the design and construction of the built world.

Unlock the value of your institutional knowledge—organized, connected, and grounded in your team's critical workflows with Nomic.

Start for free
What Is a 60% CD? 60 Percent Construction Documents | Nomic