AEC definitions

What Is a 30% CD?

Last reviewed: September 2026

A 30% CD is a construction document set that is about 30 percent complete: plans established, major systems selected, and specifications started, but details, schedules, and coordination still open. On many civil and federal jobs the same checkpoint is called 30% design, and that package is earlier than a building project’s 30% CD.

Stands for
30 percent construction documents, when the contract says CD
Often confused with
30% design, which many agencies use for an earlier package
Who issues it
The architect or engineer of record, as a formal submission
Who reviews it
The owner, and sometimes a construction manager or agency reviewer
What is still open
Most details, full specifications, and interdisciplinary coordination
Next gate
Typically 60% CD, or 60% design on the same percentage scale

Definition

30% CD (30 Percent Construction Documents)

Percent-complete milestones are review gates, not a national standard. An owner, a DOT, or a federal agency defines what 30 percent must contain, and the design contract should say which definition applies. On a building project that uses AIA phases, construction documents come after schematic design and design development, so a 30% CD set already has a settled plan and is starting the instruments the contractor will build from. On a highway or federal facility job, "30% design" is often the first formal submission and lines up closer to the end of schematic design. Treating those two packages as the same review is how teams either under-draw the submission or review it as if it were ready to bid.

In depth

30% CD and 30% design are not the same package

Architects on commercial buildings usually inherit a percentage from the owner’s project manager: 30, 60, 90, and 100 percent of construction documents. By the time CDs start, schematic design has fixed the plan diagram and design development has sized the major systems. Thirty percent of that CD effort looks like dimensioned plans, a structural grid, preliminary elevations and sections, single-line MEP, and an outline specification.

Civil and federal practice often skips the SD/DD/CD labels and submits "30% design." USACE, NAVFAC, and many DOTs expect that package to show design criteria, general arrangements, typical sections, and a preliminary cost, with plenty of the building or roadway still undecided. If a comment log from a 30% design review demands fabrication-level details, the reviewer is applying a later gate to an earlier set.

What a reviewer can fairly expect on the sheets

A solid 30% CD building set lets someone walk the floor plan and see the structural bay, the exit stairs, the shaft locations, and the rooms that drive equipment size. Wall types may be typical rather than complete. Details are the ones that set the envelope or the structure, not every condition. The project manual is usually an outline or a short-form spec, enough to price systems and not enough to buy products.

What does not belong yet is a fully coordinated reflected ceiling plan, a complete door schedule, or a specification section that names a basis of design for every product. Those land at 60 and 90 percent. The estimate at 30 percent should still carry design contingency, because the set will move.

Where 30% reviews waste the next phase

The useful comments at 30 percent are about arrangement, system choice, code strategy, and cost. A comment that asks for a missing hanger detail will be obsolete once the ceiling coordination happens. Teams that spend the review window marking missing annotation, instead of challenging the structural grid or the air-handler location, lose the last cheap moment to change the building.

The other failure is a set that is labeled 30% and drawn to 10%. Plans that are still diagrammatic cannot support a real cost check or a constructability pass. The submission requirements in the design contract, or the agency’s CAD/BIM manual, are the checklist. A percentage in the title block does not define the package by itself.

What should be closed before 60%

Thirty percent comments need a written response, the same way a later review does. Unanswered comments reappear at 60%, usually after the team has drawn them into the set the wrong way. Owners who track a comment log with a disposition (accept, clarify, or defer) get a 60% set that is actually further along.

Scope that is still an allowance or an alternate should be named as such on the 30% estimate. Letting an undefined kitchen, lab, or site package hide inside a lump-sum line makes the 60% estimate look like a blowout when it was a gap at 30.

Examples

30% CD (30 Percent Construction Documents) on a real project

  • 01

    A corporate office set issued as 30% CDs shows dimensioned plans, a structural grid, and outline specs, with most details still marked typical.

  • 02

    A state DOT 30% design submission shows alignment, typical sections, and a preliminary estimate, and it is not a construction document set.

  • 03

    An owner’s reviewer flags the exit stair width at 30% CD, because moving the stair at 90% would redraw every discipline.

FAQ

Frequently asked questions

30% CD means construction documents that are about 30 percent complete. Plans and major systems are established, and specifications and details are still in progress. The design contract or the owner’s submission manual defines the exact contents.

Often no. On many building projects, 30% CD means 30 percent of the way through construction documents, after schematic design and design development. On many civil and federal projects, 30% design is the first formal review and is closer to schematic design. Read the contract before you review the set.

Typically site and floor plans, major elevations and sections, a structural grid with framing started, preliminary MEP plans, key wall sections, and an outline specification. Full details, schedules, and a complete project manual usually come at later percentages.

The owner reviews it, often with a construction manager, a cost estimator, and agency reviewers on public work. The architect or engineer of record issues the package and responds to comments before the 60% submission.
Accelerating the design and construction of the built world.

Unlock the value of your institutional knowledge—organized, connected, and grounded in your team's critical workflows with Nomic.

Start for free
What Is a 30% CD? 30 Percent Construction Documents | Nomic