30% CD and 30% design are not the same package
Architects on commercial buildings usually inherit a percentage from the owner’s project manager: 30, 60, 90, and 100 percent of construction documents. By the time CDs start, schematic design has fixed the plan diagram and design development has sized the major systems. Thirty percent of that CD effort looks like dimensioned plans, a structural grid, preliminary elevations and sections, single-line MEP, and an outline specification.
Civil and federal practice often skips the SD/DD/CD labels and submits "30% design." USACE, NAVFAC, and many DOTs expect that package to show design criteria, general arrangements, typical sections, and a preliminary cost, with plenty of the building or roadway still undecided. If a comment log from a 30% design review demands fabrication-level details, the reviewer is applying a later gate to an earlier set.