What Is a Proposal Request?

Last reviewed: September 2026

A proposal request asks the contractor to propose a price and a time adjustment for a change the owner is considering. It is not authorization to do the work. If the owner accepts the proposal, a change order follows. If the work must start before agreement, the contract uses a change directive, not a proposal request.

Asks for
Price and time for a proposed change
Does not
Authorize the work
Issued by
Usually the architect, for the owner
Becomes
A change order, if accepted
If work cannot wait
Use a construction change directive
Not
The procurement RFP that hired the contractor

Definition

Proposal request

The architect usually issues the request, describing the change with sketches or revised sheets. The contractor prices it under the change clause: labor, material, subcontract, and the allowed markup, plus any time. The owner accepts, rejects, or negotiates. Until a change order is signed, the contract sum and the contract time are unchanged. Teams that treat the proposal request as a notice to proceed build unpaid work. Teams that call it an RFP confuse it with the solicitation that awarded the project.

In depth

Describe it so it can be priced

Attach the sketch or the revised detail. Name the spec sections. A sentence that says 'upgrade the lobby' is not priceable. The contractor's proposal should itemize, not answer with a single unexplained lump, unless the contract allows that.

Time impact is part of the proposal. A price with no days, on work that affects the critical path, is incomplete.

Use the contract's percentages

The general conditions or the supplements state overhead and profit on changes, including tiers of subcontractors. A proposal that invents a different stack will be sent back. So will a proposal that omits a markup the contract allows.

Unit prices in the contract are used where they apply, instead of a fresh lump.

The owner decides with the number in view

Accepting is a change order. Rejecting closes the request. Partial acceptance should be written so the unaccepted part is not built. The proposal's validity date matters. A number from six months ago is not a current price.

Silence is not acceptance. If the owner wants the work, the signed change order is the authorization, and the field should not start from the request alone.

When you cannot wait for the quote

If the owner needs the work to proceed before agreement, issue a construction change directive.

The proposal request path is for changes that can wait. Mixing them is how a contractor starts work on a pricing exercise.

Examples

Proposal request on a real project

  • 01

    The architect issues a proposal request with a revised finish plan. The contractor returns a price and five days. The owner signs a change order for both. Then the work starts.

  • 02

    The owner rejects the proposal. The documents stay as they were. The contractor does not build the revision.

  • 03

    The work is needed before the price is agreed. A construction change directive authorizes it. The proposal request alone would not have.

FAQ

Frequently asked questions

A written request for the contractor to price a possible change. It does not change the contract and does not authorize the work.

The proposal request asks for a number. The change order is the signed instrument that changes the price or time. You need the second one before the contract has changed.

Use the contract's construction change directive, or similar instrument, which directs the work and sets a method to determine cost. Do not treat a proposal request as that directive.

Because it requests a proposal. In procurement, RFP means the solicitation that awards a project. Use proposal request for a change so the logs stay straight.