AEC definitions

What Is a Construction Change Directive?

Last reviewed: September 2026

A construction change directive, or CCD, is a written order directing the contractor to change the work before the owner and contractor have agreed on the price or time adjustment. The work proceeds, and the adjustment is determined afterward by the method in the contract.

Stands for
Construction Change Directive
Common form
AIA Document G714
Signed by
The owner and the architect; the contractor is directed
Agreement on price
Not required before the work proceeds
Ends as
A change order once the adjustment is agreed
Wrong tool when
The change has no effect on cost or time (use an ASI)

Definition

Construction Change Directive (CCD)

A change order requires agreement. Jobsites often cannot wait for agreement: a concealed condition, an owner decision, or a code comment needs work now. AIA Document G714 is the usual CCD form. The owner signs it, the architect prepares it, and the contractor is directed to proceed. The contract then sets how cost is figured if the parties still disagree, often by mutual acceptance of a lump sum, by unit prices, or by actual cost plus a fee. When they later agree, the CCD is converted into a change order. A CCD is not a minor-change ASI, and it is not a bilateral change order.

In depth

It exists so disputed price does not stop the work

Change-order negotiation can take weeks of estimates, subcontractor quotes, and markup arguments. Meanwhile a slab is open or an inspector is scheduled. The CCD separates the direction to build from the settlement of money. The owner accepts the risk of paying by the contract’s fallback method if negotiation fails. The contractor accepts the duty to perform and to keep cost records.

Without a CCD, a verbal "just do it, we’ll sort out the cost" is a claim with bad paperwork. With a CCD, the direction, the date, and the scope are written. The fight, if there is one, is about the amount, not about whether the work was ordered.

How the adjustment gets determined

AIA general conditions typically allow the adjustment to be agreed as a lump sum, determined by unit prices in the contract, or calculated as the contractor’s actual cost plus a fee, with specified markups. The CCD itself can propose one of those. If the contractor disagrees with the proposed method or amount, the work still proceeds and the architect makes an interim determination, subject to the contract’s dispute path.

Actual-cost work needs daily records: labor, equipment, and material tickets signed in the field. Contractors who treat a CCD like a lump-sum change and skip the tickets lose the ability to prove cost. Owners who ignore the tickets and demand a lump sum later invite the same dispute.

Pick the CCD only when an adjustment is expected

If everyone agrees the change is minor and free, an ASI is the matching form. Issuing a CCD for a no-cost clarification spooks the cost report and implies entitlement that does not exist. If everyone already agrees the price and the days, skip the CCD and sign the change order. The directive is the middle case: change is required, agreement is not in hand.

Scope written on the CCD should be buildable. "Proceed with the revised lobby" without a sketch forces the contractor to guess, then price the guess. Attach the drawings or the narrative the estimator will measure.

Close it into a change order

A CCD left open through the job becomes an argument at final payment. The project manager should track each CCD with a status: issued, cost submitted, interim determination, converted to change order. The schedule of values and the pay application should not bill the work as original scope while the CCD is unresolved.

Time adjustments need the same closing. A CCD that adds days does not extend the contract until the change order says so, unless the contract provides otherwise. Leaving time "to be determined" until the end is how liquidated damages and delay claims get tangled.

Examples

Construction Change Directive (CCD) on a real project

  • 01

    An unforeseen conduit conflicts with a footing, and the owner issues a CCD so the redesign can be built before the price is settled.

  • 02

    The contractor tracks force-account labor against the CCD because the parties did not agree a lump sum.

  • 03

    CCD 4 is converted to Change Order 12 once the cost and two extra days are signed.

FAQ

Frequently asked questions

CCD means construction change directive. It directs the contractor to proceed with a change when the owner and contractor have not yet agreed how the contract sum or contract time will be adjusted.

A change order is a bilateral agreement that modifies the contract. A CCD is a direction to perform a change before that agreement exists. The CCD is typically converted into a change order once the adjustment is determined.

Under the AIA form, the owner and the architect sign the CCD. The contractor does not have to agree with the proposed cost for the directive to be effective. The contractor does have to perform the work and document the cost.

Use an architect’s supplemental instruction when the change does not affect the contract sum or the contract time. Use a CCD when a cost or time adjustment is expected and has not been agreed.
Accelerating the design and construction of the built world.

Unlock the value of your institutional knowledge—organized, connected, and grounded in your team's critical workflows with Nomic.

Start for free
What Is a Construction Change Directive (CCD)? | Nomic