ASI stands for Architect’s Supplemental Instruction. It is a written order for a minor change in the work that does not change the contract sum or the contract time. If the change affects price or time, it needs a change order or a construction change directive instead.

Stands for
Architect’s Supplemental Instruction
Common form
AIA Document G710
Who issues it
The architect, to the contractor
Cost and time
No change to contract sum or contract time
If cost or time changes
Use a change order or a construction change directive
Becomes
Part of the contract record for that minor change

Definition

ASI (Architect’s Supplemental Instruction)

AIA Document G710 is the form most firms mean by an ASI. The architect issues it to the contractor to direct a minor change consistent with the contract documents. The contractor is expected to carry it out without a cost or time adjustment. That limit is the whole point. Teams that use an ASI to move a wall, swap a system, or "clarify" work the contractor will claim, create a dispute about whether the instruction was minor. The safe test is simple: if either party expects money or days to change, stop and use the change process.

In depth

Minor means no price and no time

A minor change is a refinement the contract already contemplated: a dimension clarified, a finish location adjusted within the specified product, a detail that does not add assemblies. The contractor performs it inside the existing sum and schedule. G710 says this on its face. Ignoring that sentence is how ASIs become back-door change orders.

The contractor who believes the instruction is not minor should say so before doing the work, in writing. Performing the work and pricing it later leaves both sides arguing from memory. The architect who suspects a cost impact should not issue the ASI at all.

ASI, RFI, CCD, and change order

An RFI asks a question. The response clarifies the documents. If the clarification is a minor adjustment with no cost or time effect, the architect may follow it with an ASI so the field has a direction, not only an answer. If the answer adds scope, the next document is a proposal request and then a change order, or a construction change directive if the owner needs the work to proceed before price agreement.

A CCD, AIA G714, orders a change when the owner and contractor have not agreed on the adjustment. It assumes there will be an adjustment. An ASI assumes there will not. Using the wrong form does not change the facts of the work, and it does confuse the log the cost report is built from.

What the instruction should contain

Number it, date it, and describe the change with sheet and detail references. Attach a sketch if the words can be drawn two ways. State that the contract sum and contract time are unchanged. Copy the owner and the consultants whose sheets are affected. An ASI that revises a structural detail without the engineer’s knowledge is the architect directing work outside their license.

Consultants issue their own supplemental instructions on some jobs, under the prime architect’s cover. The contract still looks to the architect for administration. A loose PDF from a mechanical engineer labeled "direction" should be pulled into the project’s instruction log or it will never reach the coordination record.

The pattern that creates claims

A stack of ASIs that each look small can add labor, especially late, out of sequence, or in finished areas. Contractors claim cumulative impact even when each ASI said "no cost." Owners who want a clean record reserve the ASI for changes the superintendent agrees are minor, and they put everything else on a change document from the start.

The other abuse runs the opposite way: every sketch becomes a change-order request, including true clarifications. The documents have to be read. A note that restates a specification is not new scope. The form should follow the substance, not the sender’s preference.

Examples

ASI (Architect’s Supplemental Instruction) on a real project

  • 01

    The architect issues an ASI to shift a door six inches, and the contractor agrees the change has no cost or time impact.

  • 02

    A proposed ASI would add a rated shaft wall, so the team uses a change order instead.

  • 03

    An RFI response clarifies a detail, and an ASI records the minor field direction that follows from it.

FAQ

Frequently asked questions

ASI stands for Architect’s Supplemental Instruction. It is the architect’s written direction for a minor change in the work that does not change the contract sum or the contract time.

An ASI directs a minor change with no adjustment to price or time. A change order is a signed modification that does adjust the contract sum, the contract time, or both. If money or days are in play, the ASI is the wrong form.

A construction change directive orders a change when the price or time adjustment is not yet agreed, and it anticipates that an adjustment will be made. An ASI is only for changes with no adjustment. Both are post-award. Neither is an addendum.

AIA Document G710, Architect’s Supplemental Instructions. Projects using other contract families have an equivalent minor-change instrument. The label matters less than the rule: no change in sum or time.
Accelerating the design and construction of the built world.

Unlock the value of your institutional knowledge—organized, connected, and grounded in your team's critical workflows with Nomic.

Start for free
What Is an ASI? Architect’s Supplemental Instruction | Nomic