AEC definitions

What Is LOD in BIM?

Last reviewed: September 2026

LOD in BIM means level of development: how completely an element’s geometry and attached information have been resolved, and how much other team members may rely on them. It is not the same thing as how detailed the element looks on screen.

Stands for
Level of development
Not the same as
Level of detail, which describes graphic complexity
Common scale
100, 200, 300, 350, 400, and 500
Reference
BIMForum Level of Development specification
Set in
The BIM execution plan, by element and phase
Governs
What other people may rely on, not just what was drawn

Definition

LOD (Level of Development)

The BIMForum Level of Development specification, built on AIA work, defines standard LODs so a model author and a model user can share one expectation. LOD 100 is conceptual. LOD 200 is approximate geometry. LOD 300 is specific geometry you can measure. LOD 350 adds interfaces with other systems. LOD 400 is suitable for fabrication. LOD 500 is a field-verified representation. An element can be graphically busy and still be LOD 200 if the team has not agreed you may rely on its size and location. The BIM execution plan should state the LOD by element and by milestone. A single LOD for "the model" is too crude to enforce.

In depth

What each common LOD allows someone to do

At LOD 100 an element may be a symbol or a mass. You can use it for early studies, not for measurement. At LOD 200 the element has approximate size, shape, location, and orientation. You can use it to reserve space, with the understanding it will move. At LOD 300 the quantity, size, shape, location, and orientation are specific enough to coordinate and to measure from, within the uses the plan allows.

LOD 350 models the interfaces: supports, connections, and the parts needed to show how the element meets its neighbors. That is the level coordination meetings often need and design models often lack. LOD 400 adds the detail a fabricator needs to make the piece. LOD 500 records a field-verified element. It is not automatic at the end of the job. Someone has to verify it.

A pretty element can still be unreliable

Level of detail describes how much geometry is shown. Level of development describes how much thought and authorization sit behind it. A manufacturer’s highly detailed family dropped into a schematic model does not become LOD 400 because the mesh is dense. If the engineer has not designed that connection, nobody should fabricate from it.

The practical test is a sentence: "May the coordinator dimension from this, may the estimator count it, may the detailer build it?" Those can be three different answers for the same element. Write the authorized uses next to the LOD. The number alone gets misread.

LOD is a milestone promise, not a file property

A BIM execution plan attaches target LODs to phases. Structural framing might be LOD 300 at CD issue and still LOD 200 in early DD. MEP mains might reach LOD 350 only in the trade coordination model, after award. Expecting fabrication reliability from a design model because the software can display it is how owners think they bought shop drawings in the design fee.

Different elements in one model sit at different LODs at the same time. Equipment may be a specific product while the duct connecting it is still approximate. Reports that say the model is "LOD 300" without an element matrix are marketing. Ask for the matrix.

Handoffs fail at the LOD boundary

Clash detection on LOD 200 ductwork produces clashes that move when the duct is sized. That can still be useful if the meeting treats them as space reservations. Treating them as field issues wastes the trades. The coordination plan should say which LOD is in the federated model this month.

When a contractor takes over a design model for VDC, the first task is to learn what the author authorized. IFC export does not raise the LOD. It only carries what was in the source, sometimes with parameters renamed or dropped. Verify the fields you intend to rely on after the exchange.

Examples

LOD (Level of Development) on a real project

  • 01

    A BIM execution plan requires structural steel at LOD 300 for the CD issue and leaves connections to the detailer’s LOD 400 model.

  • 02

    A generic air handler at LOD 200 is used to reserve a mechanical room, not to submit a product.

  • 03

    A coordination clash on LOD 350 piping includes the hanger zone, so the fix survives into shop drawings.

FAQ

Frequently asked questions

LOD stands for level of development. It describes how resolved an element’s geometry and information are, and how much the rest of the team may rely on them.

LOD 300 means the element’s size, shape, location, and orientation are specific enough to coordinate and measure. LOD 350 also models the interfaces with other building systems, such as supports and connections needed to show how the element is attached.

No. Level of detail is about graphic complexity. Level of development is about reliability and authorized use. A visually detailed object can still be a low level of development if the team may not rely on it for coordination or fabrication.

LOD 400 means the element includes detail suitable for fabrication, including the information a trade needs to manufacture and install that component. It is typically a detailer’s model, not the automatic contents of a design model.
Accelerating the design and construction of the built world.

Unlock the value of your institutional knowledge—organized, connected, and grounded in your team's critical workflows with Nomic.

Start for free
What Is LOD in BIM? Level of Development Explained | Nomic