AEC definitions

What Is a Differing Site Condition?

Last reviewed: September 2026

A differing site condition is a physical condition at the site that was not visible and that differs materially from what the contract documents indicated, or from what a contractor would ordinarily expect. Federal practice calls these Type I and Type II. The remedy exists only if the contract includes the clause and the contractor gives prompt notice.

Type I
Differs materially from what the documents indicated
Type II
Unusual, unknown, and not reasonably expected
Notice
Usually required before the condition is disturbed
Documents
Borings, reports, and what bidders were told to rely on
Not covered
Weather, price escalation, or a careless bid
Remedy
A change in price and time, if the clause applies

Definition

Differing site condition

Type I is a material difference from conditions indicated in the documents, such as rock where the borings showed soil. Type II is an unknown physical condition of an unusual nature, which a reasonably prudent contractor would not have expected, even though the documents were silent. The geotechnical report, what it disclaims, and what the bid documents told bidders to rely on decide Type I claims. A contractor who priced without reading the borings will struggle. Notice before disturbing the condition is a common requirement, because the owner must be able to inspect. This clause is not a warranty that the site is easy. It is a narrow remedy for concealment and misindication.

In depth

Type I follows the indications

The claim compares the condition encountered with a specific indication: a boring log, a note, a drawing of existing foundations. A general disclaimer does not always wipe out a specific boring, and a specific warning can defeat a claim. Read both.

The difference has to be material to cost or time. A small variance inside what the report described is not a Type I condition.

Type II is the rarer one

The condition was unknown, physical, and unusual for the work. 'We found the soil harder than we like' is not enough if the region commonly has that soil and the documents did not say otherwise.

Type II does not require a false indication. It requires surprise of an unusual kind. Courts and boards construe it narrowly.

Stop and notify

The clause typically requires written notice before the condition is further disturbed, so the owner can investigate. Covering the evidence and claiming later is how valid conditions are denied.

The notice should describe what was found, where, and how it differs from the indicated condition. Photos and a survey help.

The reasonable bidder is the standard

A contractor is expected to review the documents and to inspect the site as the instructions require. Patent conditions, visible on a site walk, are not concealed. A bid that ignored a report the invitation included is a bidding choice.

Pre-bid RFIs that would have revealed the issue, and were obvious to ask, can matter. So can an owner who withheld a report they had.

Price the delta, not the whole job

The adjustment is the extra cost and time caused by the condition, under the change clause. It is not a chance to reprice work that matched the documents.

Contractors who excluded the clause in a proposal may have accepted the risk. Owners who deleted the clause on purpose have placed that risk in the bid. Either choice should be explicit.

Examples

Differing site condition on a real project

  • 01

    Borings show sand. Excavation hits a buried concrete foundation the drawings did not indicate. The contractor stops and gives written notice. That is a Type I path.

  • 02

    A visible slope the site walk showed is not a differing site condition. It was there to see.

  • 03

    The contractor notifies, the owner inspects, and a change order pays the extra rock removal the report did not indicate.

FAQ

Frequently asked questions

It is a concealed physical condition that differs materially from what the contract documents indicated, or an unknown condition of an unusual nature that a reasonable contractor would not have expected.

A condition that differs materially from an indication in the contract documents, such as subsurface data the bidder was told to rely on.

An unknown physical condition of an unusual nature, differing from what is ordinarily encountered, even though the documents did not indicate it one way or the other.

Stop work that would disturb the evidence and give the written notice the contract requires, describing the condition and how it differs. The owner then investigates.
Accelerating the design and construction of the built world.

Unlock the value of your institutional knowledge—organized, connected, and grounded in your team's critical workflows with Nomic.

Start for free
What Is a Differing Site Condition? | Nomic