What Is Force Account?

Last reviewed: September 2026

Force account is a way to pay for extra work using set rates for labor, equipment, and materials, plus a stated markup, when the parties cannot agree on a lump sum or a unit price in time. It is common in public works and DOT specifications. Daily records are the payment.

Pays
Labor, equipment, and materials at spec rates, plus markup
Used when
A price cannot be agreed before the extra work
Common on
Public civil and highway contracts
Record
Daily hours and equipment, verified contemporaneously
Cousin of
Time and materials on private work
Not
Permission to perform unordered work

Definition

Force account

The specification publishes how labor burden, equipment rates, and material invoices are counted, and what percentage is added. The inspector or engineer often must verify the hours on the day they are worked. Force account is time and materials under that public specification. It is not a blank approval of whatever crew showed up. Unauthorized force-account work is as unpaid as any other extra. The owner who directs it should say so in writing before the cost runs.

In depth

It is a pricing method, not a scope source

A change, a differing site condition, or a directed extra is the entitlement. Force account only prices it. Starting the crew without direction does not create the entitlement.

If a unit price already covers the item, the spec usually says to use the unit price, not force account.

Use the project's rate table

Equipment rates may follow a named guide. Labor may be actual wages plus a listed burden. Substituting a private T&M sheet on a DOT job misprices the work.

Markup on subcontractors may differ from markup on the prime's own forces. The spec will say.

Same-day verification

The inspector signs the daily extra-work report. Materials are attached with invoices. A reconstructed week is often rejected even when the work was real.

Idle equipment and a crew larger than the work needs will be challenged. Record what was required.

Some owners still set a ceiling

A force-account authorization can include a not-to-exceed amount. Hitting it means stop and reauthorize. The method is cost-based. The ceiling is a management limit.

Convert to a unit price or lump sum when the quantity becomes predictable. Force account is a poor way to pay a long, repeatable operation.

Private contracts may borrow the word

If a private subcontract says force account, define the rates in the subcontract.

Do not assume the public spec's percentages apply. If the subcontract says T&M, use that term and that rate sheet.

Examples

Force account on a real project

  • 01

    An unclassified obstruction is directed as force account. The inspector signs daily labor and equipment. Payment follows the DOT rate rules.

  • 02

    A unit-price item already covers the excavation. The engineer rejects a force-account ticket for the same work.

  • 03

    The authorization is NTE a stated amount. The contractor stops at the cap and waits for a revised order.

FAQ

Frequently asked questions

It is payment for directed extra work at specified rates for labor, equipment, and materials, plus markup, used when a lump sum or unit price is not agreed in time.

They are the same idea. Force account is the term in many public specifications, with published rate rules. Time and materials is the private-contract term, paid from an agreed rate sheet.

Usually the owner's inspector or engineer, on daily records signed when the work is done. Later reconstructions are often rejected.

No. There still needs to be a written direction or a contract clause that entitles the extra. Force account prices work that was authorized.