What Is a Deferred Submittal?

Last reviewed: November 2026

A deferred submittal is a portion of the design documents that is not submitted with the permit application but is submitted to the building official later, within a period the building official sets. The building official has to approve the deferral first, and the work cannot be installed until the deferred documents are approved.

What it is
Design documents submitted to the building official after the permit application
Approval needed
The building official must approve the deferral first
Listed by
The registered design professional in responsible charge, on the construction documents
Reviewed by
The design professional first, then the building official
Install only after
The building official approves the deferred documents
Not the same as
A contractor submittal to the architect during construction

Definition

Deferred Submittal

Some parts of a building are designed by the trade that will install them, after the permit set has gone in. Fire sprinkler layouts, fire alarm drawings, and prefabricated trusses are common examples. Rather than hold the permit until those are drawn, the building official can allow them to be deferred. The registered design professional in responsible charge lists the deferred items on the construction documents so the building official can see what is missing and approve the arrangement. The International Building Code describes the process in its administration chapter, and local jurisdictions often add their own forms and timelines.

In depth

Why a design gets deferred

Some systems cannot be fully designed until a specific manufacturer or installer is chosen. A fire sprinkler contractor produces hydraulic calculations and shop drawings for the system it will install, and a truss manufacturer designs the trusses for its own fabrication process. If the permit waited for those, projects would sit idle through the early phases.

The deferral lets the permit proceed on the design that is complete, while the dependent parts follow. It is a scheduling tool with a code process attached, and it only works if the permit documents are explicit about what is deferred and who is responsible for coordinating it.

How the process runs

The registered design professional in responsible charge identifies the deferred items on the construction documents, and the building official approves the deferral before the permit issues. Later, the trade produces the deferred documents and gives them to the design professional, who reviews them and forwards them to the building official with a notation that they have been reviewed and found to be in general conformance with the design of the building.

The building official then reviews and approves the deferred documents. Many jurisdictions publish a form for this step and set a deadline for submitting. The deferred work may not be installed until the building official has approved the documents, which makes the approval date a schedule driver for the trade.

A deferred submittal is not a contractor submittal

The two share a word and almost nothing else. A contractor submittal goes to the architect during construction to show how the contractor intends to meet the contract documents. A deferred submittal goes to the building official for permit approval, through the design professional. A single item, such as fire sprinkler shop drawings, can need both.

Mixing them up is a common source of delay. A contractor who believes the architect’s approval of a shop drawing satisfies the permit may start installing before the building official has approved the deferred documents. The project specification should tell the trade which submittals are also deferred submittals and where to send them.

How it relates to delegated design

Delegated design is a contract arrangement. The contract documents require a contractor or its design professional to design a portion of the work to stated performance criteria, and to provide sealed calculations. A deferred submittal is a permit arrangement. The two often overlap, because a delegated design item is frequently also a deferred submittal.

The distinction matters for who owns the review. The licensed design professional for the contractor’s portion seals the design. The registered design professional in responsible charge for the project reviews it for general conformance before it goes to the building official.

Examples

Deferred Submittal on a real project

  • 01

    A fire sprinkler contractor submits hydraulic calculations and shop drawings through the architect to the building official, which the plan review approved as a deferral.

  • 02

    A truss manufacturer provides engineered truss drawings that the structural engineer reviews and forwards to the building department before framing.

  • 03

    A permit set lists fire alarm as a deferred submittal, and the permit notes state the approval needed before installation.

Tooling

Where AI helps with deferred submittals

The documents carry a tracking problem. The permit set says which items are deferred, the specification says which submittals apply, and the trade’s package has to show it meets the design criteria. Checking those three against each other is a document comparison.

Nomic compares a deferred package with the permit drawings, the governing specification section, and the code references a team provides, and cites the sheet or clause for each difference. It does not replace the design professional’s review or the building official’s approval.

Compare AI tools for submittal review

Best AI for Submittal Review in 2026

FAQ

Frequently asked questions

A deferred submittal is a portion of the design documents that goes to the building official after the permit application instead of with it. The building official approves the deferral first, and the work cannot be installed until the deferred documents are approved.

Fire sprinkler systems, fire alarm systems, and prefabricated trusses are common. The list depends on the jurisdiction, which publishes its own guidance on what it accepts as deferred.

The trade that designs the item prepares it. The registered design professional in responsible charge reviews it and forwards it to the building official with a notation that it has been reviewed and is in general conformance with the design of the building.

A regular submittal goes from the contractor to the architect during construction to show how the contract documents will be met. A deferred submittal goes to the building official, through the design professional, for permit approval of a portion of the design that was not ready at application.