Why a design gets deferred
Some systems cannot be fully designed until a specific manufacturer or installer is chosen. A fire sprinkler contractor produces hydraulic calculations and shop drawings for the system it will install, and a truss manufacturer designs the trusses for its own fabrication process. If the permit waited for those, projects would sit idle through the early phases.
The deferral lets the permit proceed on the design that is complete, while the dependent parts follow. It is a scheduling tool with a code process attached, and it only works if the permit documents are explicit about what is deferred and who is responsible for coordinating it.