What Is Plan Review in Construction?

Last reviewed: September 2026

Plan review is the examination of a permit set by the authority having jurisdiction, or a third party acting for it, to confirm the design complies with the adopted building codes and local amendments before a building permit is issued. The reviewer returns written comments, the design team responds, and the cycle repeats until the set is approved.

Who performs it
Plan examiners at the authority having jurisdiction, or a third-party reviewer acting for it
What is reviewed
The permit set: drawings, specifications, calculations and supporting reports
Checked against
Adopted model codes plus local amendments in force on the submittal date
Output
A written comment or correction letter, then a backcheck of the responses
Ends with
An approved set, which is what allows the permit to be issued
Not the same as
Field inspection, which checks the work built against the approved set

Definition

Plan Review

Plan review sits between design and construction. Once a project submits for permit, plan examiners in the building department check the drawings, specifications and supporting calculations against the codes the jurisdiction has adopted: building, fire, mechanical, plumbing, electrical, energy and accessibility, plus any local amendments. Structural, fire and health reviews often run in parallel with separate reviewers. The output is a comment letter, sometimes called correction comments or plan check comments. The design team resolves each comment, resubmits, and the examiner performs a backcheck against the response. Approval of the set is what releases the permit. It is not a guarantee that the building is free of errors, and it does not transfer design responsibility away from the licensed professionals who sealed the drawings.

In depth

Who actually reviews the set

Most jurisdictions split the review across specialists rather than running it through one examiner. A building examiner covers occupancy, egress, fire separation and accessibility; a structural examiner reads the calculations against the drawings; fire, mechanical, plumbing, electrical and energy reviews may sit with different desks or different departments entirely. Public health, planning and utilities can each hold their own approval.

Many jurisdictions also accept third-party review, where a licensed consultant performs the examination and the department accepts the result. That usually buys a shorter queue, not a softer review. Either way the applicant is coordinating several reviewers with different comment styles, and a set can clear four desks while a fifth holds it.

The comment cycle is the actual work

A first submittal rarely comes back clean. The examiner issues numbered comments, each citing a code section, and the design team responds to every one in writing, usually in a comment response matrix that pairs the comment, the response and the sheet where the change appears. Resubmittal returns the revised set with that matrix attached.

Backcheck is the examiner verifying that each response does what it claims. A response that says "see revised sheet A3.02" and points at a sheet where nothing changed restarts the cycle and costs another queue slot. On a large project, three cycles is normal and each one can take weeks, which is why permit timelines are usually measured in review rounds rather than in days.

What comments are usually about

The recurring items are not exotic. Egress width and travel distance, fire-resistance ratings and the assemblies cited to achieve them, accessible route and clearance dimensions, occupancy classification and allowable area, energy compliance documentation, and structural details that the calculations do not match. Missing information generates as many comments as wrong information: an unreferenced detail or a schedule that does not agree with the plan both come back.

The other large category is internal inconsistency. Architectural sheets that disagree with structural, a specification section that names a product the drawings do not, a life-safety plan that shows a door the floor plan does not. Examiners find these because reading the set as a whole is exactly what they do.

Why plan review governs the schedule more than teams expect

Permit approval is a hard gate. No amount of contractor readiness moves it, and the project cannot buy its way past a queue. Review times vary widely by jurisdiction and project type, from a couple of weeks for a small tenant improvement to several months for a complex building, and each resubmittal usually re-enters the queue rather than jumping it.

That makes the quality of the first submittal worth real money. A set that generates 40 comments instead of 120 does not just save response hours, it can save an entire review round. Teams that run an internal check against the code before submitting are buying schedule, not tidiness.

Plan review, drawing review and inspection are three different things

Plan review is the jurisdiction checking a permit set against adopted code. Drawing review is the design and construction team checking its own documents for coordination, completeness and constructability, which happens before submittal and continues through construction administration. Inspection happens on site and checks the work built against the approved set.

The terms blur in software marketing, where "AI plan review" is often used for any automated check of a drawing set. The distinction that matters to a practitioner is who holds the authority: only the jurisdiction can approve a permit set, and no internal or automated check changes that.

Examples

Plan Review on a real project

  • 01

    A city plan examiner returns 62 numbered comments on a first submittal, half of them citing egress and accessibility sections of the adopted code.

  • 02

    A design team resubmits with a comment response matrix pairing each comment with a response and the revised sheet, and the examiner backchecks the responses.

  • 03

    A developer hires a third-party reviewer accepted by the jurisdiction to shorten the queue on a phased industrial permit.

Tooling

Where AI helps before the set goes to the jurisdiction

The useful place for software is the submittal a team controls: reading the set against the code edition and amendments in force, flagging the provisions a reviewer is likely to comment on, and finding the internal contradictions between drawings, schedules and specifications that generate comments for no good reason. That is a checking pass over documents the team already has, and it is worth doing before a review round is spent on it.

Nomic reads the drawing set alongside the specification and the code library and cites the sheet or section behind every finding, so an engineer can confirm each one rather than trust it. It does not issue permits and it does not stand in for the authority having jurisdiction, whose review is the only one that approves a set.

Compare AI tools for plan review

Best AI for Plan Review in 2026

FAQ

Frequently asked questions

Plan review is the examination of a permit set by the authority having jurisdiction, or a third party acting for it, to confirm the design complies with adopted building codes and local amendments. The reviewer issues written comments, the design team responds and resubmits, and the examiner backchecks the responses before the set is approved and the permit is issued.

Plan examiners in the building department, usually split by discipline across building, structural, fire, mechanical, plumbing, electrical and energy. Many jurisdictions also accept third-party review by a licensed consultant, in which case the department accepts that reviewer’s result.

It varies by jurisdiction, project type and how many disciplines review in parallel, from a couple of weeks on a small tenant improvement to several months on a complex building. Each resubmittal generally re-enters the queue, so the number of comment cycles usually matters more to the schedule than the length of any single review.

Plan review checks the documents before construction, against the adopted codes. Inspection checks the constructed work on site against the approved set. One approves what is proposed, the other verifies what was built.

A backcheck is the examiner verifying that the design team’s written responses actually resolve each comment in the resubmitted set. Responses that point at changes the drawings do not show send the set back into another cycle.

No. Approval confirms the set satisfied the reviewer on the code provisions examined. Responsibility for the design stays with the licensed professionals who sealed the drawings, and errors found later are still theirs to correct.
Accelerating the design and construction of the built world.

Unlock the value of your institutional knowledge—organized, connected, and grounded in your team's critical workflows with Nomic.

Start for free
What Is Plan Review? Permit Sets, Comments and Backcheck Explained | Nomic