The work is interpretation of the documents
An RFI asks what the documents require. A submittal shows what the contractor intends to provide. A site visit compares visible work with those documents. A change, if one is needed, is issued through an ASI, a CCD, or a change order. CA is that loop, plus the logs that keep it from living in inboxes. Engineers of record administer their own disciplines, usually through the architect.
Response times are in the specifications or the general conditions. A late submittal review can delay fabrication as surely as a late shop drawing. CA staffing should match the volume. A fee that assumed a quiet job will not survive a hospital’s submittal count, and the drawings will not review themselves.