What acceptance should check
A finish on or before the contract date, logic that a builder recognizes, procurement for long-lead items, and ties to the schedule of values if the spec requires cost loading. A pretty bar chart with every activity linked only to the finish is not reviewable.
Constraints and lags should be explained in the narrative. Hidden constraints are how float is manipulated.