What Is a Notice to Proceed?

Last reviewed: September 2026

A notice to proceed, or NTP, is the owner’s written direction authorizing the contractor to start the work. On most contracts the NTP date starts the contract time. It is not the award letter, and it is not permission to ignore required submittals or permits.

Stands for
Notice to proceed
Issued by
The owner, sometimes through the construction manager
Usually starts
Contract time, including the date for substantial completion
Different from
A notice of award, which selects the contractor
Limited form
Authorizes only named early work
Does not replace
Permits, insurance, or required preconstruction submittals

Definition

Notice to Proceed (NTP)

Award means the owner has selected a contractor. The agreement may be signed before anyone is allowed to mobilize. The notice to proceed is the separate authorization to begin, dated, and it usually starts the clock for substantial completion. A limited NTP can authorize only early work, such as submittals or demolition, while the full notice waits on a permit or financing. Starting work before any NTP, because the job "is obviously going," puts cost and time outside the contract’s measurement. The letter should say what is authorized, what date governs, and which documents are the contract set.

In depth

Award and NTP are different dates on purpose

Notice of award tells the bidder they were selected and usually demands bonds, insurance, and the signed agreement within a set number of days. None of that, by itself, authorizes crews on site. Owners wait to issue the NTP until those conditions are met, and sometimes until a permit is in hand. The gap is intentional.

Contract time measured from award instead of from NTP punishes the contractor for the owner’s delay in issuing the notice, unless the contract says that is the deal. Read the time article. "Days from NTP" and "days from execution" are different projects.

A limited notice is not a quiet full notice

A limited NTP lists the work allowed: submittals, procurement of long-lead items, demolition, or a site package. Anything else is not authorized, and payment should be limited to the listed scope. Contractors who mobilize the whole job on a limited notice and then claim delay when the full NTP slips are arguing a letter they did not read.

Owners who issue a limited NTP because the permit is incomplete should not expect construction duration to start. If the clock starts anyway, the owner is spending float before the contractor can build. Write whether contract time starts, and for which portion.

The notice does not waive other conditions

Insurance, bonds, safety plans, and baseline schedules are often conditions precedent. An NTP issued before they arrive, or work started in reliance on a verbal NTP, leaves a hole when something goes wrong in week one. The notice should acknowledge which conditions are satisfied and which are still required before related work.

Permits can sit with the owner or the contractor depending on the contract. An NTP is not a building permit. The authority having jurisdiction does not treat the owner’s letter as authorization to build. Field work without the permit is an enforcement problem on top of a contract problem.

The baseline schedule needs this date

The contractor’s baseline CPM should use the NTP date as the start, or the date the contract specifies. A schedule that starts "when we get the permit" with no data date will not prove a delay later. If the NTP is limited, the baseline should show only the authorized path and a milestone for the full notice.

Delay claims measure entitlement against this start. Lost letters and undated emails are why owners and contractors both keep the NTP in the contract file, not in a project manager’s inbox. The date on the letter is the date. A kickoff meeting is not a substitute.

Examples

Notice to Proceed (NTP) on a real project

  • 01

    The owner issues an NTP dated March 1, and substantial completion is required 400 days later.

  • 02

    A limited NTP allows submittals and equipment release only, and the full notice waits on the building permit.

  • 03

    A notice of award requires bonds within ten days, and the NTP is withheld until the bonds are delivered.

FAQ

Frequently asked questions

NTP means notice to proceed. It is the owner’s written authorization for the contractor to begin the work described in the notice. The contract usually measures completion time from that date.

A notice of award selects the contractor and typically requires bonds, insurance, and a signed agreement. A notice to proceed authorizes the start of work and usually starts contract time. Award does not, by itself, put crews on site.

A limited NTP authorizes only the work it names, such as submittals, procurement, or demolition. Other work remains unauthorized until a full notice is issued. Payment and schedule impacts should match that limit.

No. The NTP is a contract document between owner and contractor. A building permit is permission from the authority having jurisdiction. Both can be required before field work starts.
Accelerating the design and construction of the built world.

Unlock the value of your institutional knowledge—organized, connected, and grounded in your team's critical workflows with Nomic.

Start for free
What Is a Notice to Proceed in Construction? | Nomic