Logic makes the path, not the longest bars
An activity is critical because of what it is tied to, not because it looks important. Drywall can be critical and concrete can have float if the logic says the end date runs through the finishes. Schedulers name predecessors and successors: finish-to-start is the common tie. Missing ties, or ties that run everything back to a single milestone with no real sequence, produce a path that will not survive a delay claim.
Calendars matter. A cure time on a seven-day calendar and crew work on a five-day calendar change the math. So do constraints that force a date. A constraint that pins substantial completion to the contract date can manufacture negative float and hide which field activity is actually late. Know which constraints are in the file.