AEC definitions

What Is a Look-Ahead Schedule?

Last reviewed: September 2026

A look-ahead schedule is a short-horizon plan, commonly three weeks, that says what crews will do, what must be delivered, and which inspections must happen. The superintendent uses it to coordinate. It should be consistent with the baseline schedule. It does not replace the baseline, and it is not, by itself, a delay analysis.

Horizon
Often three weeks, sometimes six
Author
The superintendent, with the trade foremen
Checks
Constraints: design, materials, access, inspection
Must agree with
The current project schedule
Does not replace
The baseline CPM
Updated
Weekly

Definition

Look-ahead schedule

Each week the team drops the expired week, adds a new one, and checks constraints: drawings approved, materials on site, predecessor complete, inspector booked. Work that is not ready is not scheduled as if it were. That make-ready step is the point. A look-ahead that lists everything the baseline hoped for, without checking constraints, is a wish. Pull planning and last-planner practices use look-aheads this way. The contractual CPM remains the baseline.

In depth

Screen the work before you promise it

For each activity, ask whether the submittal is approved, the material is released, the predecessor is actually done, and the inspection is scheduled. If the answer is no, the activity stays off the look-ahead or is flagged.

Putting unready work on the plan trains the trades to ignore the plan.

The meeting is short and specific

Foremen commit to the week. The superintendent removes conflicts. Decisions that need the project manager, such as an unpaid extra, are sent out of the room into the change process. The look-ahead is not a place to approve scope.

Write the commitments down. Next week's meeting starts by comparing them to what happened.

Reconcile to the CPM

If the look-ahead slips an activity that is critical, the monthly update must show it. Running a cheerful three-week plan while the CPM shows negative float is two projects. One of them is fiction.

The baseline's activity names should be recognizable on the look-ahead so the connection is obvious.

It is a progress record, not a claim schedule

A stack of look-aheads shows what the field intended. It rarely has the logic a delay analyst needs.

Keep it. Do not let it become the only schedule on the job.

Examples

Look-ahead schedule on a real project

  • 01

    The three-week look-ahead lists a slab pour only after rebar inspection is booked and the vapor barrier is on site.

  • 02

    A promised duct delivery misses. The next look-ahead pulls that work off and the monthly update shows the slip.

  • 03

    Foremen review last week's commitments before they take new ones.

FAQ

Frequently asked questions

A short-term field schedule, often three weeks, used to coordinate labor, deliveries, and inspections. It should match the project schedule.

The baseline is the approved plan for the whole job. The look-ahead is the near-term slice the field commits to. Both should tell the same story.

Checking that constraints are cleared before an activity is placed on the look-ahead. Work that is not ready is not promised.

It is supporting evidence of what the field planned. The contractual analysis usually needs the baseline and the updates, with logic.
Accelerating the design and construction of the built world.

Unlock the value of your institutional knowledge—organized, connected, and grounded in your team's critical workflows with Nomic.

Start for free
What Is a Look-Ahead Schedule? | Nomic