How the series are organized
The letter identifies what the document does. The A series covers owner-contractor agreements and related documents such as the general conditions and bonds. The B series covers owner-architect agreements. The C series covers other agreements, including architect-consultant arrangements. The D series is miscellaneous. The E series holds exhibits, including digital practice exhibits. The F series covers facility maintenance documents. The G series holds contract administration and project management forms.
AIA also groups documents into families by project type, such as the stipulated sum, cost-plus, construction manager as constructor, and design-build families. Documents in the same family use common terms and adopt each other by reference, so mixing forms from different families without checking the cross-references can leave a defined term pointing at the wrong document.