Addenda exist so every bidder prices the same project
A question from one bidder, if it reveals an ambiguity, should not be answered only to that bidder. The fair instrument is an addendum to the whole plan room. That is different from an RFI during construction, which is a contractor’s question after award. During bidding, the pre-bid question and the addendum are the pair.
Public procurement rules are strict about this. A change emailed to one general contractor and not to the others will not survive a bid protest. The addendum log, the issue date, and the acknowledgment line are the evidence that the playing field stayed level.