What Is a Special Inspection?

Last reviewed: September 2026

A special inspection is an observation or test the building code requires for specific work, performed by a qualified special inspector rather than only by the city building inspector. Concrete, structural steel, soils, sprayed fireproofing, and some firestopping are typical. The permit set includes a statement of special inspections.

Required by
The adopted building code, often IBC Chapter 17
Listed in
A statement of special inspections
Performed by
A qualified special inspector, usually hired by the owner
Not
A substitute for the building inspector
Types
Continuous or periodic, as the code states
Records
Reports to the building official and the engineer

Definition

Special inspection

IBC Chapter 17, as adopted, lists which inspections are continuous and which are periodic. The registered design professional prepares the statement. The owner usually hires the agency, so the inspector is not the contractor's employee. Reports go to the building official. A failed inspection means the work is not accepted, even if it is already covered. Scheduling the inspector is a construction activity. Forgetting it and burying the rebar is a tear-out.

In depth

The statement is a permit document

It lists the inspections, the frequency, and the wind or seismic category that triggered them. The structural notes and the statement should match. A boilerplate list that includes tests the project does not need, or omits ones it does, will be corrected in plan check or in the field.

The contractor's schedule should include hold points for continuous inspections.

Independence is the point

The agency reports deviations to the contractor for correction and to the engineer and building official. A contractor who hires and directs the inspector, where the code forbids that, has not provided the inspection.

Qualifications are defined. A general superintendent is not a special inspector because they watched the pour.

What gets inspected

Structural concrete placement, reinforcement, high-strength bolts, welds, soils compaction, sprayed fire-resistive materials, and smoke control are common. The list is the project's, not a universal one.

Fabricators with an approved shop program may have different shop-inspection rules. The statement should say so.

Final reports are a certificate condition

The building official may withhold the certificate of occupancy until final special-inspection reports and a completion letter are in.

Track them like submittals. They are easy to forget because they are not a product.

Examples

Special inspection on a real project

  • 01

    The statement requires continuous inspection of structural concrete. The pour does not start until the inspector is on site.

  • 02

    A bolt inspection is periodic. The inspector verifies the marked connections on the schedule in the statement.

  • 03

    Final special-inspection reports are submitted before the certificate of occupancy is requested.

FAQ

Frequently asked questions

It is a code-required inspection of specific structural or fire-resistive work by a qualified special inspector. It supplements, and does not replace, the building official's inspections.

Typically the owner, or the owner's agent, so the inspector is independent of the contractor. The adopted code states the rule.

The document, prepared by the design professional, that lists each required special inspection and whether it is continuous or periodic. It is submitted for the permit.

The building official can require it to be exposed and removed if it cannot be verified. Schedule the inspector before the hold point.
Accelerating the design and construction of the built world.

Unlock the value of your institutional knowledge—organized, connected, and grounded in your team's critical workflows with Nomic.

Start for free
What Is a Special Inspection? | Nomic