AEC definitions

What Is a Certificate of Occupancy?

Last reviewed: September 2026

A certificate of occupancy, or CO, is the document from the authority having jurisdiction that says a building may be occupied because it complies with the adopted codes. A temporary certificate, a TCO, allows occupancy with listed conditions still open. Neither one is the contractor’s certificate of substantial completion.

Abbreviation
CO; TCO for a temporary certificate
Issued by
The authority having jurisdiction, usually the building department
Based on
Inspections against the approved permit documents and adopted codes
TCO means
Occupancy allowed with stated conditions and often an expiry
Not issued by
The architect or the general contractor
Different from
Substantial completion under the construction contract

Definition

Certificate of Occupancy (CO)

The building department, sometimes with the fire marshal, inspects completed work against the approved permit set. When the inspections pass, it issues a certificate of occupancy. A TCO allows occupancy before every last item is closed, with conditions and an expiration. Opening to the public without one, where the local code requires it, is an enforcement problem for the owner. The contractor’s contractual milestone is separate: substantial completion says the owner can use the work under the contract. An owner can hold a TCO and still have a punch list, retainage, and unfinished closeout with the contractor.

In depth

It allows occupancy under the code

The certificate states the occupancy the building was approved for. Using it differently, or occupying a floor the certificate does not cover, exceeds what the inspection approved. Mixed-use buildings may be phased, with a CO or TCO for one portion while another is still a construction site. The separation between those portions has to match what the inspector accepted.

Life-safety systems are the usual gate: egress, fire alarm, sprinklers, emergency lighting, and the final inspections those trades require. A finished lobby with an untested alarm does not get a CO because the furniture is in. The inspection list is the city’s list, and it will not match the contractor’s punch list one for one.

A TCO is permission with homework

Temporary certificates exist so an owner can occupy while non-safety items remain, or while a seasonal test is outstanding. They list conditions and a date. Missing the date without a renewal means the permission lapsed. Treating a TCO as a permanent CO because people have already moved in is how a project discovers an expired occupancy the week of a complaint.

The conditions should be someone’s contractual scope. If the TCO requires a remaining stair guard and the contractor considers that punch, the contract has to say who finishes it and who is liable if it is late. The city will not sort the change-order log. The city will pull the permission.

Do not merge it with substantial completion

Substantial completion is certified under the owner-contractor agreement, usually by the architect, and it moves warranties, damages, and retainage. The CO is certified by the inspector and moves the legal right to occupy. They can happen the same week. They answer different questions. An owner who moves in on a TCO before substantial completion should have a written early-occupancy agreement covering insurance, warranties, and liquidated damages.

The inspector reviews the approved permit set. The contract enforces the issued-for-construction set, including addenda. If those diverged, a CO can be issued for a configuration the contract does not describe, or withheld for a permit comment the bid set never picked up. Reconcile the two sets before the final inspections, not in the lobby on inspection morning.

Paper the inspections the way the city asks

Special inspections, elevator inspections, health-department sign-off, and fire-alarm acceptance are common predecessors. Each has a report. A missing report holds the certificate even when the work is visible and correct. Someone on the contractor or owner team should own the matrix of sign-offs, with the same seriousness as the submittal log.

After the CO, alterations that change egress or occupancy classification need their own permits. The original certificate is not a permanent waiver. Facilities teams inherit this, which is why the CO and the approved set belong in the closeout record next to the O&M manuals.

Examples

Certificate of Occupancy (CO) on a real project

  • 01

    The building department issues a TCO for floors 2 through 4 with a condition that the fire-alarm test report be filed within 30 days.

  • 02

    The contractor reaches substantial completion while the CO is still held for a failed elevator inspection.

  • 03

    A phased CO covers the renovated wing, and the original wing keeps its existing certificate.

FAQ

Frequently asked questions

It is the official document from the building department, or other authority having jurisdiction, stating that a building complies with the adopted codes and may be occupied for the use stated on the certificate.

A CO is the final certificate. A TCO is a temporary certificate that allows occupancy while listed conditions remain, usually with an expiration date. Those conditions have to be closed or the TCO renewed.

No. The city issues the certificate of occupancy under the building code. The architect certifies substantial completion under the construction contract. One governs legal occupancy. The other governs warranties, time, and payment between owner and contractor.

The contract assigns it, often to the contractor for assembling inspections and to the owner as the permit holder. The authority having jurisdiction is the only party that issues it. The architect does not.
Accelerating the design and construction of the built world.

Unlock the value of your institutional knowledge—organized, connected, and grounded in your team's critical workflows with Nomic.

Start for free
What Is a Certificate of Occupancy? CO and TCO | Nomic