AEC definitions

What Is QA/QC in Construction?

Last reviewed: October 2026

QA/QC stands for quality assurance and quality control, and it is also written QAQC, QA-QC or QCQA. Quality assurance is the process a project puts in place to prevent defects; quality control is the inspection and testing that verifies completed work meets the contract requirements. QA controls how the work is done, QC verifies the result, and a complete quality program runs both.

Stands for
Quality assurance and quality control
QA is
Process-focused and preventive — built up front
QC is
Product-focused and verifying — applied to completed work
Where they meet
The Inspection and Test Plan, and its hold points
When work fails
A nonconformance report records the deviation and the fix

Definition

QA/QC in Construction

QA/QC in construction covers two related but distinct disciplines. Quality assurance is proactive and process-focused: the project quality plan, the procedures, the standards the team agrees to work to, the training, and the review workflows designed so that work is built correctly the first time. Quality control is reactive and product-focused: the inspections, material tests, checklists and reviews that verify completed work actually meets the contract requirements. In practice the two run together through an Inspection and Test Plan, which sets out what gets checked, by whom, at which hold points, and against which standard.

In depth

Quality assurance versus quality control

The two halves get conflated constantly, and the conflation is expensive. Quality assurance is what you build before the work starts: the quality plan, the procedures, the standards, the review workflows, the training. Quality control is what you do to the work after it exists: inspect it, test it, measure it against the requirement.

A project with strong QC and weak QA finds a lot of defects. A project with strong QA finds fewer, because fewer were created. Both are necessary, but they are not interchangeable, and a quality program that is all inspection is a program that has decided to pay for rework.

Working out which one you are being asked for

The fastest way to tell them apart on a live project is to ask what the activity produces. If it produces a document that tells somebody how to work, it is quality assurance: the project quality plan, a procedure, a qualification of a supplier, a checklist written before anyone uses it, a review of the drawings before they are issued. If it produces a record of whether something already built meets the requirement, it is quality control: an inspection report, a test result, a punch item, a nonconformance.

The second question people really mean when they ask "QA or QC" is who owns it. QA is typically owned above the project, because consistency across projects is the point and a procedure rewritten per job is not a procedure. QC is owned on the project, because the work being verified only exists there. A firm whose QA lives entirely in individual project managers' habits has quality control and calls it a quality program, which is a distinction that stays invisible until a defect repeats on a third project.

The documents a quality program actually produces

There are four, and a project missing any of them has a gap worth naming. The project quality plan states who is responsible for what, which standards apply, and how nonconformances get resolved. The Inspection and Test Plan breaks that down per activity with hold and witness points. Inspection and test records are the evidence each check was done and what it found. Nonconformance reports capture what deviated, why, the corrective action, and the verification that closed it.

On the design side the equivalents are the drawing review checklist, the markup record, and the back-check confirming comments were incorporated. These get skipped more often than the field documents because nobody inspects them, which is exactly why errors that should have been caught in review turn up later as RFIs. Owners increasingly ask for the design-side records too, and a team that cannot produce them is relying on the reviewer having remembered.

The Inspection and Test Plan and its hold points

The Inspection and Test Plan is where QA and QC meet in practice. It lists each activity, the standard it is checked against, who performs the check, what evidence gets recorded, and — critically — which points are hold points where work stops until the inspection passes.

Rebar before a pour is the classic example: once the concrete is placed, an error that would have taken an hour to fix becomes a demolition problem. Getting hold points right is the highest-leverage quality decision on most projects, and it happens on paper months before anyone pours anything.

What happens when something fails

The nonconformance report is the mechanism. An NCR records what deviated, why, and what the corrective action is, and it stays open until the correction is verified. It is the paper trail that proves a defect was found, addressed, and re-checked.

The discipline that separates a functioning quality system from a paperwork exercise is whether nonconformances feed back into the QA side. If the same nonconformance recurs across three projects, the problem is not the crew — it is the procedure or the documentation that led them there.

Design-side QA/QC on drawings and specifications

The same logic applies to documents. Before a set is issued, someone checks that plans, sections, elevations and schedules agree with each other, that keynotes point to the right specification sections, that the fire rating on the plan matches the assembly in the spec, and that code-driven requirements actually appear in the drawings rather than only in the code analysis.

This review is the cheapest quality intervention available on any project, and it is the one most often compressed when a deadline moves. Errors that survive it do not disappear — they reappear as RFIs, as change orders, and occasionally as failed inspections.

Examples

QA/QC in Construction on a real project

  • 01

    An Inspection and Test Plan sets a hold point requiring rebar inspection before any concrete pour.

  • 02

    A concrete cylinder break test at 28 days verifies the mix met the specified compressive strength.

  • 03

    A design-side QA review catches a fire rating on the plan that does not match the wall assembly called out in the specification.

Tooling

Where AI helps with QA/QC

Cross-referencing a drawing set against its own specification is systematic, tedious work with a well-defined right answer — exactly the profile where software beats an exhausted reviewer the night before an issue date. Automated checking can flag where a plan, a schedule and a specification section disagree, and cite the page for each.

What it does not do is exercise judgment about whether a detail will actually perform, or decide whether a flagged discrepancy matters. The reviewer still owns that. Nomic is a document-side verification layer, not a field inspection platform and not a substitute for a quality manager.

Compare AI tools for construction QA/QC

Best AI for QA/QC Reviews in 2026

FAQ

Frequently asked questions

QA/QC stands for quality assurance and quality control. Quality assurance is the set of processes, plans and standards put in place to prevent defects. Quality control is the inspection, testing and review that verifies completed work meets the contract requirements.

QA is proactive and process-focused — the quality plan, procedures, training and review workflows that make correct work more likely. QC is reactive and product-focused — the inspections, tests and checklists applied to work that already exists. QA prevents defects; QC catches the ones that get through.

An Inspection and Test Plan lists each activity on a project, the standard it is checked against, who performs the check, what evidence is recorded, and which points are hold points where work stops until the inspection passes. It is the document where quality assurance and quality control meet in practice.

A nonconformance report, or NCR, records work that deviated from the requirement, why it happened, and the corrective action. It stays open until the correction is verified. Recurring nonconformances signal a problem in the procedure or the documents rather than in the crew.

Yes. Design-side QA/QC checks that plans, sections, schedules and specifications agree with each other before a set is issued, that keynotes reference the right specification sections, and that code requirements appear in the drawings. It is the cheapest point at which to catch an error.

QAQC means quality assurance and quality control, the two halves of a construction quality program. It is written several ways, including QA/QC, QA-QC, QA QC and occasionally QCQA, and they all refer to the same pair. Quality assurance is preventive and process-focused: the plan, procedures, standards and reviews put in place before work starts. Quality control is verifying and product-focused: the inspections, tests and checklists applied to work that already exists.

QA/QC is the program. Quality control automation is a method applied inside it, where a check that a person used to perform by eye is performed by software instead. The useful candidates are checks with a defined right answer and a high volume of repetitions: whether every element in a schedule has a corresponding callout, whether a fire rating on a plan matches the assembly in the specification, whether a submitted product meets the specified performance value. Automating those does not replace the program, and it does not remove the judgment call about whether a flagged discrepancy matters.

Four at minimum: the project quality plan stating responsibilities, applicable standards and the nonconformance process; the Inspection and Test Plan setting out each activity, its standard, its evidence and its hold points; the inspection and test records themselves; and nonconformance reports with their corrective actions and verification. Design-side work has equivalents that are skipped more often: the drawing review checklist, the markup record, and the back-check confirming comments were incorporated before issue.
What Is QA/QC in Construction? QA vs QC Meaning Explained | Nomic