AEC definitions

What Is a Mechanical (HVAC) Plan?

Last reviewed: November 2026

A mechanical plan, also called an HVAC plan, is the floor plan in the mechanical set that shows ductwork, diffusers and grilles, HVAC equipment, and often hydronic piping. It gives duct sizes, the airflow in cubic feet per minute at each air device, and tags that point to the equipment schedules, and it is drawn to the mechanical and energy codes the jurisdiction adopts.

1234567ABCGUEST ROOM301GUEST ROOM302GUEST ROOM303GUEST ROOM304GUEST ROOM305GUEST ROOM306GUEST ROOM307GUEST ROOM308GUEST ROOM309GUEST ROOM310GUEST ROOM311GUEST ROOM312GUEST ROOM313GUEST ROOM314GUEST ROOM315GUEST ROOM316GUEST ROOM317GUEST ROOM318GUEST ROOM319STAIRS224x14AHU-127'-3"27'-0"27'-3"27'-3"27'-0"27'-3"94'-8"1AHVAC PLANSCALE: 1/8" = 1'-0"N1234CONSULTING ENGINEERSREVISIONSPROJECTRIVERSIDE HOTELSCALE1/8" = 1'-0"DATE11/21/2026KEY PLANSHEET TITLEHVAC PLANSHEET NUMBERM-101

What you're looking at

HVAC Plan, annotated

A mechanical plan with supply and return ductwork, diffusers, and the equipment that serves each zone.

  1. 1Main supply duct, sized width by depth
  2. 2VAV box feeding the zone
  3. 3Supply diffuser at the end of the branch
  4. 4Return grille
Sheet series
M-100 plans, with schedules and details later in the set
Shows
Ductwork, air devices, equipment, dampers, often piping
Air device tags
Device type, neck size, and airflow in CFM
Governing codes
IMC or UMC, ASHRAE 62.1 ventilation, ASHRAE 90.1 or IECC energy
Duct construction
SMACNA standards referenced in the specification
Coordinated with
Structure, the RCP, sprinklers, and electrical connections

Definition

Mechanical plan

Mechanical plans are numbered in the M-100 series. On most commercial projects the ductwork plan and the piping plan are separate sheets, because supply, return, and exhaust duct already fill a floor before chilled water, heating hot water, condensate, and refrigerant piping are added. Larger projects draw duct double-line at its real width so conflicts with beams and other trades are visible, while small tenant work often uses single-line duct where routing is mostly diagrammatic.

In depth

Airflow numbers are the design

Each supply diffuser, return grille, and exhaust register carries a tag with its device type and airflow, such as a 12 by 12 diffuser at 250 CFM. Those numbers add up to the capacity of the air handler or rooftop unit on the schedule, and they come from the load calculation and the ventilation calculation for each space.

When a room changes use, its airflow changes too. A storage room turned into a conference room needs more outside air under IMC Section 403 and ASHRAE 62.1, plus more cooling, so the diffuser count, the branch duct size, and sometimes the unit selection all move.

Duct steps down as the air is delivered

The main trunk leaving the unit is the largest duct on the plan, and each takeoff lowers the airflow downstream, so the duct steps down in size. Rectangular duct is called out width by depth, with the first number being the side seen in plan, and round duct by diameter.

Depth is the constraint that matters most. A 24 by 16 duct may fit under a beam where a 20 by 20 duct carrying the same air will not, so the drafter checks the ceiling height on the RCP, the structural framing, and the sprinkler mains before settling on a size.

Fire and smoke dampers follow the architecture

Where a duct passes through a fire-rated wall, a fire barrier, a shaft enclosure, or a smoke barrier, IMC Section 607 may require a fire damper, a smoke damper, or a combination fire smoke damper. The mechanical plan shows each one, and where they go depends on the architect's life safety plan and wall types.

Dampers need access for inspection and testing, so each one implies an access door in the duct and often an access panel in a hard ceiling. A rated corridor wall that moves on the architectural background can add or remove a dozen dampers at once.

Equipment tags connect four disciplines

Tags such as RTU-1, AHU-2, VAV-3-12, and EF-4 point to the equipment schedules, which list capacity, airflow, electrical characteristics, operating weight, and the basis of design. The electrical engineer circuits from those values, the structural engineer checks the weight on the roof, and the plumbing engineer picks up the condensate.

A late substitution with a different voltage, weight, or curb size is a change on four sets of drawings. Keeping the schedule, the plan tag, and the electrical connection in sync is a large share of the revision work on a mechanical set.

Layer discipline keeps a crowded plan readable

Supply, return, and exhaust duct sit on separate layers within the M-HVAC group of the US National CAD Standard, so each system can be colored, frozen, or plotted at its own weight. Equipment, piping, and annotation each get their own layers too.

Overlaying the mechanical plan on the RCP and the sprinkler plan is how teams find diffusers landing on light fixtures and sprinkler heads trapped above wide duct. When a duct widens in a revision, the fire protection designer may have to add heads below it.

Examples

Mechanical plan on a real project

  • 01

    M-102 shows RTU-2 feeding a 30 by 14 supply main down the corridor, with four 10 inch round branches to diffusers tagged CD-1 at 220 CFM each.

  • 02

    A combination fire smoke damper is added where the supply main crosses the 1-hour corridor wall, with a 12 by 12 access door noted on the duct.

  • 03

    A conference room conversion raises outside air from 45 to 160 CFM, and the VAV box, branch duct, and diffuser tags are revised and clouded.

Tooling

Drafting and checking ductwork plans

Nomic lays out duct and air devices on the architectural background in CAD on its own computer, sizes the duct from the airflow and friction criteria your engineer sets, tags devices and equipment, and saves the DWG on your layers and blocks. It reads equipment cutsheets for connection sizes and follows how your firm drew ductwork on past projects.

It checks the plan against the IMC and ASHRAE editions you name and against the RCP and equipment schedules, clouds what it drew, and lists open questions such as rated walls with no damper shown. Load calculations, equipment selection, and the final call stay with the mechanical engineer of record, who reviews and stamps the sheet.

Best AI for HVAC design

Best AI for HVAC Design in 2026

FAQ

Frequently asked questions

Ductwork with sizes, supply diffusers, return and exhaust grilles with airflow, HVAC equipment with tags, fire and smoke dampers, and on many projects hydronic and refrigerant piping on a separate sheet.

In most firms they mean the same sheet. A mechanical set can also include piping plans, controls diagrams, and on small projects plumbing, so mechanical is the broader term.

Cubic feet per minute, the airflow each diffuser, grille, or piece of equipment is designed to deliver or remove.

The International Mechanical Code or Uniform Mechanical Code as adopted, ASHRAE 62.1 for ventilation where referenced, and the adopted energy code, usually ASHRAE 90.1 or the IECC.