Why it is mirrored
If you drew the ceiling as you see it looking up, left and right would swap relative to the floor plan and every overlay would be backwards. Reflecting it keeps grid A on the same side of the sheet as grid A on the plan.
That convention trips people up once. After that, the rule is simple: the RCP and the floor plan share an orientation. A device that looks 'on the wrong side' is usually a real conflict, not a mirror error. Check before you assume the drafter flipped it.
What belongs on the RCP
Ceiling materials and heights, soffits, bulkheads, light fixtures, air devices, sprinkler heads, speakers, and access panels. A height note should say what it measures: to finish ceiling, to the grid, or to the deck.
The specification and the finish legend define the ceiling product. The RCP shows where each type occurs. A tag with no legend, or a legend type that the spec does not include, is incomplete.
The plenum is the coordination problem
The RCP shows the finished surface. The section and the mechanical drawings show what has to fit above it. A 9 foot ceiling under a 12 foot deck is not 3 feet of clear plenum once beams, fireproofing, and hangers are counted.
Coordination meetings should carry the RCP, the structural framing plan, and the mechanical sheet together. Moving a diffuser on the RCP without checking the duct that feeds it only moves the problem.
How the installer uses it
The ceiling trade lays out grid from the RCP. The other trades penetrate that grid at the devices shown. A revision to the RCP after grid is delivered is a cost event, even when the architectural change looks small.
As-built marks on the RCP, for devices that moved, matter at closeout because the facilities team will look up from this sheet. A record set that still shows the bid-day diffuser layout is not a record.