AEC definitions

What Is an Equipment Schedule?

Last reviewed: September 2026

An equipment schedule is a table on the drawings that lists pieces of equipment, keyed by a mark, with the capacity, size, and electrical data the design requires. The plans show where the mark sits. The specification states quality. The submittal has to satisfy both the schedule and the spec.

Lives on
The discipline's drawings
Keyed by
A mark that also appears on the plan
States
Capacity, configuration, and power
Paired with
The specification section for that equipment
Checked at
Submittal review and purchase
Basis of design
A representative product, not a waiver of the numbers

Definition

Equipment schedule

Mechanical, plumbing, kitchen, and electrical drawings each use schedules. A mark such as AHU-1 on the plan must be AHU-1 on the schedule, with airflow, static pressure, and power. If the schedule and the spec disagree, you have a conflict to resolve before purchase. A basis-of-design column names a representative product. It is not permission to ignore the performance numbers. Contractors price and submit from the schedule. A schedule that says 'see spec' for every value is not a schedule.

In depth

One mark, one piece, one row

Orphan marks on the plan and orphan rows on the schedule are the first coordination check. Renaming a unit in a meeting without changing both is how the wrong unit is ordered.

Quantities should be explicit when one row covers multiple identical units.

The numbers are the design

Airflow, cooling capacity, horsepower, voltage, and weight are what the structure, the electrical service, and the energy model rely on. A lighter submittal that misses capacity is not a saving.

Electrical data on a mechanical schedule must match the panel schedule's circuit. Three different horsepower numbers is a coordination miss.

Performance in both places has to match

If the schedule says 10,000 cfm and the spec says 8,000, the submittal will pick one. Edit them together. Put options and acceptable manufacturers where your office standard says, and do not contradict them on the other sheet.

Accessories, such as disconnects and vibration isolation, should be columns or spec sentences, not assumptions.

Review against the row

The cut sheet is marked to the scheduled configuration. Deviations are listed.

Approved-as-noted must say which number changed, because a changed electrical load revises the panel schedule too.

Examples

Equipment schedule on a real project

  • 01

    AHU-1 on the plan matches a schedule row with airflow, static pressure, and a 460 volt motor. The panel schedule feeds that motor.

  • 02

    The basis-of-design manufacturer is named. The submittal uses an allowed alternate that meets every scheduled number.

  • 03

    A kitchen schedule's gas load is coordinated with the plumbing riser.

FAQ

Frequently asked questions

A table on the drawings listing each piece of equipment, its mark, and the performance and electrical data required. Plan tags point to the rows.

The schedule states the project's numerical requirements and marks. The specification states quality, standards, and execution. Submittals must meet both.

A representative product that shows the level of performance. Substitutes still have to meet the scheduled capacities and the specification.

The set is uncoordinated. Add the row or delete the mark before bid or purchase. Do not let the vendor choose.
Accelerating the design and construction of the built world.

Unlock the value of your institutional knowledge—organized, connected, and grounded in your team's critical workflows with Nomic.

Start for free
What Is an Equipment Schedule? | Nomic