AEC definitions

What Is a Lump-Sum Contract?

Last reviewed: September 2026

A lump-sum contract, also called a stipulated sum, pays the contractor one fixed price to complete a defined scope. If the work costs less, the contractor benefits. If it costs more, the contractor pays the difference, except for changes and for risks the contract assigns to the owner.

Also called
Stipulated sum or fixed price
Pays
One price for the defined scope
Contractor carries
Their own overruns inside that scope
Owner pays extra for
Changes and contractually owner-side risks
Typical award
Low bid on a complete set
Not
A GMP, which is still cost-based under a cap

Definition

Lump-sum contract

The price is only as fixed as the scope is clear. Drawings, specifications, and inclusions define what the sum buys. Owner changes, differing site conditions, and owner-caused delay adjust the sum through change orders. A lump sum is the usual result of an invitation for bid. It is a poor fit for a scope that is still moving, unless the owner enjoys a stream of changes. A GMP is not a lump sum: the owner pays cost up to a cap and often shares savings. A lump sum does not open the books.

In depth

The sum follows the documents

The agreement should incorporate the drawings, specifications, addenda, and accepted alternates. A proposal exclusion survives only if the agreement gives it priority.

Ambiguous scope becomes a change argument. Money spent clarifying the bid set is cheaper than money spent litigating the lump sum.

Fixed does not mean frozen

Owner-directed work, design errors, and conditions the contract assigns to the owner still change the price and often the time. The change process is part of a lump-sum job, not a failure of it.

Contractors who bid low and hunt changes will find only the changes the documents support. Owners who rewrite the job informally will pay for it.

The schedule of values slices the sum

Applications for payment break the lump sum into line items. The total of the lines must equal the contract sum. Overbilling a early line and starving a later one is a schedule-of-values problem, not extra contract value.

Retainage is withheld from the sum under the contract. It is not an extra discount.

Compare it with the other prices

Cost-plus pays actual cost. GMP pays actual cost up to a maximum. Unit price pays measured quantities. Lump sum pays the bid. Pick the one that matches how complete the documents are.

Converting a lump sum to cost-plus midstream is a new deal. Do it with an amendment.

The contractor prices the risk they own

Productivity, buying out subcontractors, and ordinary weather they accepted are inside the number. They are not later claims. Escalation is inside the number only if the contract has no escalation clause.

A bid that assumes a perfect set on an incomplete set is not a clever lump sum. It is a claim.

Examples

Lump-sum contract on a real project

  • 01

    A school is awarded at a stipulated sum of a stated price, including two accepted alternates. The agreement lists the drawings and addenda.

  • 02

    The owner adds a classroom. A change order increases the lump sum. The original scope stays fixed.

  • 03

    The schedule of values totals the contract sum. Pay applications draw down those lines.

FAQ

Frequently asked questions

It is a fixed price for a defined scope. The contractor is paid that sum, adjusted only for changes and for risks the contract gives the owner.

Stipulated sum. AIA owner-contractor agreements use that term.

A lump sum is a fixed price, and the contractor does not show cost. A GMP pays allowable cost plus a fee, not to exceed a maximum, and unused amounts follow the savings clause.

Yes. Change orders adjust it for owner changes and for events the contract says are not the contractor's risk. The base scope does not get repriced because it was harder than the contractor hoped.
Accelerating the design and construction of the built world.

Unlock the value of your institutional knowledge—organized, connected, and grounded in your team's critical workflows with Nomic.

Start for free
What Is a Lump-Sum Contract? | Nomic