An invitation for bid, also called an invitation to bid, asks contractors to submit a price to build a defined set of documents. On public work the award often goes to the lowest responsive, responsible bidder. The design is meant to be complete enough that price is the main variable.

Also called
Invitation to bid, or ITB
Asks for
A price on issued bid documents
Public award
Often the lowest responsive, responsible bidder
Changed by
Addenda, issued before the bid deadline
Security
Often a bid bond or bid security
Not
A request to propose a different design

Definition

Invitation for bid

The invitation states the project, the bid date, the place, the bond requirements, and how documents are obtained. Addenda change the documents before bids are opened. A bid that takes exception, or that misses an addendum, can be nonresponsive. This is different from an RFP, where the owner expects to score approach as well as price. Private owners can invite bids and still negotiate. The invitation should say whether they will.

In depth

Responsive means you bid what was asked

The form, the alternates, the acknowledgments of addenda, and the signatures have to be complete. A lower number on the wrong form can be thrown out.

Responsible is a separate test: whether the bidder can do the work. The invitation should say what evidence is required, such as a license or a bond.

The bid set is the scope

Drawings, specifications, the bid form, and geotechnical information referenced by the invitation are what the number is based on. A hallway conversation is not.

If the set is incomplete, the remedy during bidding is an RFI and an addendum, not a qualified bid the owner did not allow.

Sealed bids are a procedure

Public openings read the prices aloud. That transparency is the point of an IFB. Private invitations may say the bids will be private. Follow the sentence you published.

Late bids are late. The invitation's clock is the one that counts.

Every bidder must have the same set

Addenda are acknowledged on the bid form. Opening bids when one bidder did not receive addendum 2, and the others did, invites a protest.

The last addendum should leave enough time to price it. If it does not, extend the bid date in that addendum.

Award is a notice, then a contract

A notice of award, bonds, and the signed agreement follow the opening. The invitation itself is not the contract. Notice to proceed starts the clock the agreement defines.

Bid shopping after a public opening is constrained by the rules and by the subcontractor listing laws some states impose. Know which ones apply before you re-trade the number.

Examples

Invitation for bid on a real project

  • 01

    A school district issues an IFB. Bids are sealed. The low responsive bidder who provides the required bond is awarded the work.

  • 02

    Addendum 2 changes a finish. Bidders acknowledge it on the form. A bid that does not is nonresponsive.

  • 03

    A private owner invites bids and reserves the right to negotiate. The invitation says so, which a public IFB often cannot.

FAQ

Frequently asked questions

It is a solicitation that asks contractors for a price on a defined set of construction documents. Public owners often must award the lowest responsive, responsible bid.

An IFB buys a price on a complete design. An RFP asks for a proposal and can score qualifications and approach along with price.

The bid followed the instructions: right form, addenda acknowledged, no forbidden exceptions, required security included.

Yes, by addendum, issued to all bidders in time for them to price it. The bid form should make each bidder acknowledge every addendum.
Accelerating the design and construction of the built world.

Unlock the value of your institutional knowledge—organized, connected, and grounded in your team's critical workflows with Nomic.

Start for free
What Is an Invitation for Bid? | Nomic