Two documents define what "works" means
The owner’s project requirements, the OPR, are written in the owner’s language: temperature ranges, filtration, redundancy, operating hours. The basis of design is the engineer’s response: system types, criteria, and assumptions. Commissioning without both becomes a test of whatever was installed. The CxA reviews the design to see whether the documents can satisfy the OPR, which is cheaper than discovering the gap at functional testing.
Those reviews produce comments, like any other design review. They are not a second engineer of record. The mechanical and electrical engineers still seal the design. The CxA’s comments that die in a folder do not change the equipment schedule.