The seal means responsible control
Licensing boards require the sealing architect to have responsible control over the documents. That means they directed the work, reviewed it, and can answer for it. Rubber-stamping another firm’s set, or sealing sheets they did not review, is a license problem and a liability problem. Owners should be able to name the AOR at the time the CD contract is signed.
The standard of care is professional skill and care ordinarily provided on similar projects, not a guarantee that the building will be perfect or that the cost will match an early estimate. The construction contract, not the architect’s seal, is what obligates the contractor to build what the documents show.