AEC definitions

What Is a Power Plan in Electrical Drawings?

Last reviewed: November 2026

A power plan is the electrical floor plan that shows where receptacles, equipment connections, and other power outlets go, and how each one is circuited. Homerun arrows and tags such as LP-2A-14 tell the electrician which panel and circuit feed each device, and every circuit on the plan must match the panel schedule.

1234567ABCUNIT501UNIT502UNIT503UNIT504UNIT505UNIT506AMENITY507UNIT508UNIT509UNIT510UNIT511UNIT512UNIT513STAIRS2LP-2A-1LP-2A-3LP-2A-5LP-2A-7LP-2A-9LP-2A-11LP-2A-13LP-2A-15LP-2A-17LP-2A-19LP-2A-21LP-2A-23LP-2A-25LP-2A27'-3"27'-0"27'-3"27'-3"27'-0"27'-3"94'-8"1APOWER PLANSCALE: 1/8" = 1'-0"N1234CONSULTING ENGINEERSREVISIONSPROJECTCEDAR LOFTSSCALE1/8" = 1'-0"DATE02/25/2026KEY PLANSHEET TITLEPOWER PLANSHEET NUMBERE-101

What you're looking at

Power Plan, annotated

An electrical power plan drawn over the architectural background, with receptacles circuited back to the panel.

  1. 1Duplex receptacle on the wall it serves
  2. 2Branch circuit wiring between devices
  3. 3Homerun arrow with panel and circuit number
  4. 4Panelboard the circuits return to
Sheet series
E-100 plans, such as E-111 Power Plan Level 1
Shows
Receptacles, dedicated circuits, equipment connections, panels, disconnects
Circuit tag
Panel name and circuit number, such as LP-2A-14
Must match
The panel schedule and the one-line diagram
Governing code
NEC Articles 210, 220, and 406 as adopted locally
Drawn over
The architectural background, usually attached as an xref

Definition

Power plan

Power plans sit in the E-100 series of the electrical set, drawn over a screened architectural floor plan. Lighting is normally on its own plan, so the power plan carries convenience receptacles, dedicated circuits, floor boxes, mechanical and kitchen equipment connections, disconnects, and the panelboards themselves. Every symbol is a device the electrician has to rough in, and every circuit tag assumes a breaker with spare capacity on the panel schedule. When the furniture plan moves, the power plan is usually the first electrical sheet that has to follow.

In depth

Every symbol is rough-in work with a mounting height

A duplex receptacle, a quad, a GFCI receptacle, a floor box, and a junction box for hardwired equipment each have their own symbol in the legend, and a subscript often carries a mounting height or a type letter. Anything off the standard height, such as receptacles at 42 inches above a counter or a TV outlet at 60 inches, needs a note, or the installer will set it at the office default of 18 inches.

Equipment connections show how each load connects: a junction box for a hardwired water heater, a disconnect beside a rooftop unit, a receptacle for a cord-and-plug ice machine. The mechanical and food service equipment schedules decide which of those applies, so an equipment change on another discipline's sheet is an electrical change too.

Circuiting is where the plan and the panel schedule meet

Devices on one circuit are joined with an arc, and a homerun arrow carries the panel and circuit numbers back to the panelboard. A tag like LP-2A-14,16,18 means three circuits share one raceway, which brings in ampacity adjustment for more than three current-carrying conductors and the multiwire branch circuit rules in NEC 210.4.

Every circuit number on the plan should appear on the panel schedule with the same description and a load, and every non-spare row on the schedule should land on some plan. Orphans in either direction are a routine plan check comment, and they multiply each time a background update moves devices without anyone re-circuiting them.

Code sets the minimums, and the program sets the rest

In dwelling units, NEC 210.52 drives receptacle placement: no point along a wall line more than 6 feet from a receptacle, at least two 20 amp small-appliance circuits serving the kitchen counters, and separate countertop spacing rules. NEC 210.8 lists where GFCI protection is required and NEC 210.12 lists where arc-fault protection is required, and both lists have grown with recent editions.

Commercial spaces have fewer placement mandates, so the owner's program and the furniture plan drive the counts. The load still counts: NEC 220.14(I) assigns 180 volt-amperes to each single or multiple receptacle on one yoke, which is why a corridor of convenience outlets fills a panel sooner than people expect. NEC 210.63 also requires a service receptacle within 25 feet of rooftop heating, air-conditioning, and refrigeration equipment.

The background moves, and the power plan has to follow

Power plans are drawn over an architectural background, usually an external reference (xref), so wall changes come through on reload. Attach versus overlay matters when the electrical file is itself referenced by others: an attached xref nests into the next file, and an overlaid one does not.

A wall that moves 18 inches can put a receptacle inside a door swing or behind new casework, and the reload will not flag it. The drafter has to walk the plan after each background update, move devices, and confirm the circuits still make sense, which is the most repetitive part of keeping a power plan current.

Coordination failures show up as field changes

Floor boxes need slab coordination with structure, especially in post-tensioned slabs where coring is restricted. Receptacles in fire-rated walls need listed boxes and the membrane penetration limits in IBC Chapter 7, so the architect's wall types have to say which walls are rated.

Kitchen, laboratory, and owner-furnished equipment are where power plans most often go wrong, because that equipment is selected late. A plan showing a 208 volt single-phase connection for a unit that ships three-phase means a new breaker, a new conductor set, and a change order.

Examples

Power plan on a real project

  • 01

    E-112 Power Plan Level 2 shows 14 duplex receptacles in an open office circuited as LP-2A-1,3,5, with a note that furniture feeds come from floor boxes FB-1 through FB-6.

  • 02

    A rooftop unit gets a fused disconnect and a service receptacle within 25 feet, both circuited to panel RP-1 and listed on that panel's schedule.

  • 03

    After an architectural background update, three receptacles that landed inside a relocated door swing are moved and clouded, and their circuit tags stay the same.

Tooling

Drafting and checking power plans

Nomic lays out receptacles and equipment connections on the architectural background in CAD on its own computer, circuits them to the panels you name, and saves a DWG on your layers, blocks, and tags. It follows how your firm drew power on past projects, down to the homerun tag format and the mounting height notes.

It checks the plan against the NEC edition you name and against the panel schedule, clouds everything it drew, and lists open questions such as equipment with no voltage on its schedule. Load decisions, panel sizing, and the final call stay with the electrical engineer of record, who reviews and stamps the sheet.

Best AI for electrical design

Best AI for Electrical Design in 2026

FAQ

Frequently asked questions

Receptacles, floor boxes, dedicated circuits, equipment connections, disconnects, and panels, with circuit tags and homerun arrows back to each panel. Lighting is usually on a separate plan.

The power plan shows outlets and equipment connections. The lighting plan shows luminaires, switching, and lighting controls. Both are electrical floor plans on the same architectural background, and small projects often combine them on one sheet.

It names the panel, LP-2A, and the circuit number, 14, that feeds the devices on that circuit. The arrow shows where the conductors leave the device run and head back to the panel.

In the United States, the National Electrical Code as adopted by the jurisdiction, mainly Article 210 for branch circuits, Article 220 for load calculations, and Article 406 for receptacles. Energy codes such as ASHRAE 90.1 can also require automatically controlled receptacles in some spaces.