AEC definitions

What Are Liquidated Damages?

Last reviewed: September 2026

Liquidated damages are a stated amount, usually per day, that the contractor pays the owner for finishing after the contract date. The parties agree the figure in advance as a reasonable estimate of the owner's loss, because actual delay damages would be hard to prove. A number that is a punishment, rather than an estimate, is a penalty, and penalties are often unenforceable.

Form
Usually a fixed amount per day of delay
Purpose
Agreed estimate of delay loss, not a fine
Clock
Often tied to substantial completion
Stops for
Delays the contract treats as excusable or compensable
Penalty risk
A number with no relation to likely loss
Set when
At signing, not after the project is late

Definition

Liquidated damages

The clause should say which date it runs from, usually the date of substantial completion, and which delays stop the clock, such as owner-caused delay and excusable weather if the contract allows. Charging liquidated damages for a delay the owner caused is the dispute. The amount should be set when the contract is signed, from a real estimate: rent, extended financing, lost operations. Copying a daily number from another project is how the clause becomes a penalty. Liquidated damages are not the owner's only remedy unless the clause says they are exclusive.

In depth

Build the number from the owner's costs

Extended construction loan interest, temporary facilities the owner pays, and lost use of a facility can be estimated before day one. Write down the basis. A round number chosen because it 'feels serious' is the one a court may refuse.

Different milestones can carry different amounts. A late generator may not be worth the same day-rate as a late building, if the contract distinguishes them.

Time extensions come first

A time extension for owner delay, weather the contract excuses, or a change order moves the date. Liquidated damages run only after the adjusted date. Computing them from the original date while changes are unresolved inflates the claim.

The schedule update is the evidence. A bar chart nobody maintained will not prove which delay was critical.

Say whether the daily amount is the whole remedy

Some clauses make liquidated damages the owner's only recovery for late completion, and preserve actual damages for other breaches. Others allow the owner to choose. Ambiguity here is expensive.

Actual damages plus liquidated damages for the same day of delay is double recovery unless the clause carefully separates the harms.

Subcontracts should match

A prime contractor who owes liquidated damages and whose subcontract has no pass-down of delay will pay the owner out of pocket. Flow the concept down with a rate that fits the trade's influence, not automatically the full prime rate on every sub.

A sub who can show the critical delay was someone else's should not carry the whole daily amount.

Assess them in writing

The pay application or a formal notice should show the days, the adjusted contract date, and the math.

Surprise deductions without a time determination guarantee a claim.

Examples

Liquidated damages on a real project

  • 01

    The contract sets a daily amount based on the owner's rent and loan carry. Substantial completion is 10 days after the adjusted date. The deduction is 10 times the daily amount.

  • 02

    A change order adds 15 days. Those days are not assessed. Damages run only past the new date.

  • 03

    A daily amount copied from a larger project, with no estimate of this owner's loss, is challenged as a penalty.

FAQ

Frequently asked questions

They are a daily sum fixed in the contract for late completion, meant as a reasonable estimate of the owner's delay costs rather than a punishment.

They are not supposed to be. If the amount is not a genuine pre-estimate of loss, a court may treat it as an unenforceable penalty. The label in the contract does not control.

After the contract completion date, as adjusted by time extensions. Many clauses use substantial completion as the milestone that stops the damages.

Only if the clause preserves that right. Many clauses make liquidated damages the exclusive remedy for delay.
Accelerating the design and construction of the built world.

Unlock the value of your institutional knowledge—organized, connected, and grounded in your team's critical workflows with Nomic.

Start for free
What Are Liquidated Damages? | Nomic