What Is a Demolition Plan?

Last reviewed: November 2026

A demolition plan is a drawing that shows which existing walls, doors, ceilings, finishes, equipment, and systems are to be removed and which are to remain before new work begins. Items to be removed are typically drawn dashed with keynotes describing the scope, and existing construction to remain is drawn solid.

1234567ABCLAB301LAB302LAB303LAB304LAB305LAB306LAB307LAB308LAB SUPPORT309OPEN LAB310LAB SUPPORT311LAB SUPP312LAB SUPP313STAIRS21234EXISTING TO REMAINREMOVE1REMOVE PARTITION AND BASE, PATCH FLOOR27'-3"27'-0"27'-3"27'-3"27'-0"27'-3"94'-8"1ADEMOLITION PLANSCALE: 1/8" = 1'-0"N1234CONSULTING ENGINEERSREVISIONSPROJECTWESTFIELD LABSSCALE1/8" = 1'-0"DATE02/25/2026KEY PLANSHEET TITLEDEMOLITION PLANSHEET NUMBERAD-101

What you're looking at

Demolition Plan, annotated

A demolition plan with existing walls to remain, partitions to remove, and keynotes tied to the scope.

  1. 1Partition to be removed, drawn dashed
  2. 2Keynote tied to the demolition notes
  3. 3Existing construction to remain
  4. 4Finish removal area
Sheet series
AD, MD, ED, and PD sheets, such as AD-101
To be removed
Dashed lines with keynotes
To remain
Solid lines, often screened
Drawn from
Existing conditions drawings and field verification
Regulations
OSHA 29 CFR 1926 Subpart T and the EPA asbestos NESHAP
Followed by
New work plans on the same background

Definition

Demolition plan

Demolition plans appear in renovation and tenant improvement sets for every discipline. Architects issue AD sheets such as AD-101, and mechanical, electrical, and plumbing engineers issue MD, ED, and PD sheets for their own systems, following the discipline designator modifiers in the US National CAD Standard. Each one is drawn from an existing conditions drawing, so its accuracy depends on how well the existing building was surveyed. The demolition plan defines the contractor's removal scope, and work that is not shown is a likely change order.

In depth

Line type and keynotes carry the scope

Most demolition plans draw items to be removed dashed and existing to remain solid or screened, with a legend stating the convention. Keynotes describe each scope item: remove partition to underside of deck, remove door and frame and salvage for reuse, remove ceiling and grid, protect existing to remain.

In CAD, the same distinction lives in layers. The US National CAD Standard's status field marks existing to demolish as D and existing to remain as E, so one existing conditions file can produce both the demolition plan and the new work background by freezing layers instead of redrawing.

MEP demolition is mostly about what stays live

Electrical demolition notes remove devices and wiring back to the source, mark the breaker spare on the panel schedule, and maintain circuits that serve areas outside the work. Mechanical and plumbing demolition caps piping at the main, removes duct back to a defined point, and keeps systems running for occupied floors.

The make-safe note matters most. A demolished partition with a live circuit passing through it to the next suite is both a hazard and a service interruption, so the electrical demolition plan should show what passes through the area as well as what serves it.

Accuracy depends on the existing conditions survey

Demolition plans inherit every error in the existing conditions drawing. A partition shown in the wrong place, a duct main nobody surveyed, or a panel relabeled years ago surfaces as a field condition once demolition starts.

Notes such as verify in field and contractor to confirm existing conditions protect the design team but shift risk to the contractor, and bidders price that risk. A site walk with photos of panels, nameplates, and above-ceiling conditions before the plan is drawn reduces how many of those notes are needed.

Hazardous materials come first

Under the EPA asbestos NESHAP in 40 CFR Part 61, Subpart M, a regulated facility has to be inspected for asbestos before renovation or demolition. Lead paint, PCBs in old light ballasts and caulk, and mercury in thermostats and lamps are often surveyed at the same time, and abatement is usually its own scope on separate drawings or in the specification.

OSHA 29 CFR 1926.850 requires an engineering survey by a competent person before demolition begins, covering the condition of framing, floors, and walls. That survey is the contractor's responsibility, and the demolition plan and structural notes give it a starting point.

Structural removals need an engineer

Removing a bearing wall, cutting a new slab opening, or taking out a column requires a structural design and often temporary shoring. The architectural demolition plan should point to the structural drawings for those items instead of describing them in a keynote.

Even nonstructural demolition can affect structure. Removing a topping slab, coring for new plumbing, or cutting into a post-tensioned slab needs scanning and the structural engineer's review before the cut.

Examples

Demolition plan on a real project

  • 01

    AD-101 shows three partitions dashed with keynote 4, remove partition to underside of deck, and the existing corridor wall solid with keynote 12, protect existing to remain.

  • 02

    ED-101 notes that circuits LP-3B-7 and 9 serve the adjacent suite and must stay energized, while receptacles in the demolished partitions are removed back to the junction box above the ceiling.

  • 03

    A keynote for an existing door reads remove door and hardware and salvage to owner, and the door appears on the salvage schedule.

FAQ

Frequently asked questions

A drawing that shows which existing construction, equipment, and systems are to be removed and which are to remain, usually with dashed lines for removal and keynotes describing each item.

They usually mark existing items to be removed. Solid or screened lines show existing construction to remain. The legend on the sheet states the convention for that set.

On renovation projects, usually yes. Architectural, mechanical, electrical, and plumbing demolition plans each cover that discipline's removals, and structural drawings cover any structural removals and shoring.

Under the EPA asbestos NESHAP, regulated facilities must be inspected for asbestos before renovation or demolition. State and local rules may add their own requirements.