AEC definitions

What Is a Coordination Drawing?

Last reviewed: September 2026

A coordination drawing is a combined overlay, usually produced by the contractor during construction, that shows how two or more trades will install their work in the same space. It is built from shop drawings, not from the design model alone.

Produced by
The contractor, from trade shop drawings
Required by
Often Division 01, in congested zones
Shows
How multiple trades occupy one space
Signed by
The trades whose work appears on the overlay
Not a substitute for
The design set, or a shop drawing approval
Comes after
Design coordination and shop drawing preparation

Definition

Coordination drawing

The design team's coordination happens on the contract drawings before they are issued. Coordination drawings come later. The mechanical, electrical, plumbing, fire protection, and sometimes framing trades lay their shop drawings over a shared background so sleeves, hangers, and mains can be installed once. Division 01 often requires them above ceilings, in shafts, and in crowded equipment rooms. Signing the overlay is how each trade accepts the route.

In depth

When the field needs an overlay

Corridors, shafts, equipment rooms, and anywhere a reflected ceiling plan shows a tight plenum are the usual zones. The specification should name them. If it does not, the superintendent still needs the overlay before hangers go in, because the first trade to hang pipe wins the space by default.

A coordination drawing is a construction-phase document. Asking the design team to produce it as a CD deliverable mixes two scopes, unless the contract expressly moved that work to the architect or a VDC consultant.

What the sheet should show

Background grids, elevations of each main, hanger zones, access panels, and the ceiling. Dimensions that locate the work other trades have to avoid. A color or layer per trade so a reviewer can see who owns the line.

A pretty composite that has no elevations is a picture, not a coordination drawing. The installer needs to know which system is lowest, and where a valve can still be reached after the ceiling closes.

Sign-off is the point

Each trade signs the zones it accepts. A trade that will not sign should mark the conflict with a dimension, not a general objection. The contractor resolves it or sends an RFI when the contract drawings cannot contain the work.

An RFI that says the trades do not fit, without the overlay and the elevation that failed, is hard for the engineer to answer. The coordination drawing is the attachment.

Shop drawing approval is a different stamp

The architect or engineer reviews shop drawings for conformance with the design. The coordination drawing records that the trades have agreed on a route. One stamp does not do the other job. A shop drawing can be approved and still clash with a neighbor that was submitted a week later.

Sequence the submissions so the composite is updated when a late approval moves a main. An overlay signed against an old shop drawing is how prefabricated racks show up short.

Models and the sheet the crew holds

Many projects build the overlay in a coordination model. The crew still needs a sheet or a view with elevations and a sign-off. A model only the VDC lead can open does not instruct the foreman on the morning the inserts are drilled.

If the contract asks for both, say which one governs when they disagree. The usual answer is the signed drawing, updated to match the model the trades accepted.

Examples

Coordination drawing on a real project

  • 01

    Above a hospital corridor, the mechanical contractor publishes a composite with duct, cable tray, and medical gas at stated elevations. Each trade signs before hangers are shot.

  • 02

    A shaft overlay shows the plumbing stacks and the electrical riser on opposite walls, with a note that the structural opening is 4 inches smaller than the shops assumed. The RFI goes out with the overlay attached.

  • 03

    An equipment room composite is revised after the approved air handler submittal changes the coil pull space.

FAQ

Frequently asked questions

It is the contractor's combined drawing of two or more trades in one space, made so the work can be installed without each trade claiming the same elevation. It is usually required above ceilings, in shafts, and in equipment rooms.

The contractor, often led by the mechanical trade or a VDC coordinator, using the shop drawings of the trades involved. The design team reviews conflicts that the contract documents cannot resolve.

A shop drawing shows one trade's fabrication. A coordination drawing overlays several trades to prove they fit together. Both can be required. Approval of one is not approval of the other.

Only if the contract says so. Normally they are a construction aid required by Division 01. They do not change the design. A conflict they reveal is resolved by RFI, ASI, or change order.
Accelerating the design and construction of the built world.

Unlock the value of your institutional knowledge—organized, connected, and grounded in your team's critical workflows with Nomic.

Start for free
What Is a Coordination Drawing? | Nomic