Why concrete work has joints at all
A slab, wall, or foundation is often larger than a crew can place before the first concrete begins to set. The contractor divides the work into placements, and the structural drawings or specifications indicate the permitted locations. Planning those locations puts the stops where the structure can tolerate them, usually where shear and bending are low, rather than wherever the trucks ran out.
The number of joints also drives the schedule, because each placement needs its own formwork, crew, and inspection before concrete is delivered.