Keep three dates straight
Substantial completion: the architect agrees the work is ready for use. TCO or CO: the city agrees people may occupy. Beneficial occupancy: the owner actually does. Write all three in the log. They answer different questions.
Liquidated damages usually look at substantial completion. Insurance and the correction period may look at that date or at occupancy. Read the clause. Do not use one phrase for all three.