The agreement is the definition
Read who signs, whose contingency is shared, and what happens if cost exceeds the target. If the builder still holds a traditional GMP and the architect still holds a traditional fee with no shared pool, you have a different delivery method and a collaborative culture.
Target value design, pull planning, and a big room are practices. They can be used without IPD. They do not create shared risk by themselves.